In accordance with Article 28 of the Securities Market Law, Sole Ordered Text approved by Supreme Decree No. 093-2002-EF, and the Regulation of Relevant Information and Reserved Information, approved by Resolution SMV No. 005-2014-SMV-01, we are pleased to inform that today Lima Airport Partners S.R.L. and Consorcio Inti Punku - formed by Sacyr Construcción S.A., Peruvian Branch, Sacyr Construcción Perú S.A.C. and Cumbra Perú S.A. ("Cumbra") - have signed an addendum to the "Design, Engineering, Procurement and Construction (EPC) Contract", signed by said parties on September 30, 2021, for the execution of the works related to the new passenger terminal, known as "Work Package 3 - Terminal", which are part of the "Jorge Chávez International Airport Expansion Project".

The addendum to the Contract includes the resizing of infrastructures, which increase the airport's capacity, and the inclusion of new facilities in the scope of the works included in said Contract.

The amount of the addendum is USD 350,000,000.00, plus VAT, increasing the total amount of the contract to USD 1,051,944,342.43, plus VAT. The execution term is 36 months.

Finally, Cumbra - a company that is part of the AENZA Group - has a 49% participation in the Inti Punku Consortium.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

AENZA SAA published this content on 14 November 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 14 November 2022 11:33:10 UTC.