As part of the transformation program in the Facade Access division to deliver significantly improved margins over time,
The expected annual cost savings generated by the consolidation of the assembly activity is estimated to be
Those one-off costs could be partially offset by the capital gain resulting from the divestment of the Mammendorf real estate (
The consolidation only targets the assembly workshop in Mammendorf, while R&D, engineering functions and service would be maintained in
One of the most significant projects that involves the Mammendorf facility is
The above items affecting comparability imply that the operating profit will be negatively impacted by an estimated total of
MSEK | TOTAL | One-off | EBITA impact | Expected in | |
Q4 2023 | 2024 | 2025 | |||
Mammendorf one-off costs | -95 | -40 | -55 | ||
Real estate divestment | 30 | 30 | |||
Sydney Harbour project | -45 | -45 | |||
TOTAL | -110 | -85 | -55 | 30 | |
Expected annual recurring cost savings of |
Cash outflows affecting comparability should occur in 2024.
© Modular Finance, source