Alphamin Resources Corp. provided Mpama South commissioning update. Commissioning of the Mpama South processing plant is progressing well albeit a few weeks behind the company's target of tin production from early April 2024.

The Company's processing and engineering team is now part of the final commissioning and the SMPPEI (structural, mechanical, piping and platework, electrical and instrumentation) contractor's labour complement is reducing as its activities scale down. The Mpama South underground development continues on target and ore stockpiles are being established ahead of the plant. The crusher circuit has produced approximately 5,300 tonnes of crushed ore for the hot commissioning of the jigging, gravity and fine tin plant areas.

Representatives of the original equipment manufacturer of the crusher are on site attending to the replacement of a failed mechanical unit. The mine has replacement spares for this unit while the matter is being addressed.