Arabian Cement Company received a statement from the contractor stating that he was unable to complete the project. Therefore, ACC is currently evaluating the general situation of the project, technically and contractually, to choose the best way to complete the remaining works of the project, after evaluating the technical and commercial offers from the main original equipment manufacturer. The company also confirms that it retains all contractual and financial rights from the contactor until the completion of the project.

Reasons for Exceeding the Announced End Date: The contractor, China National Building Materials Company (CNBM), did not comply with the schedule, as he informed the company of the inability to complete the project and the necessity of involving a third party.