Arabian Cement Company announced that due to the fact that the contractor (CNBM) was unable to arrive to Saudi Arabia to resume project activities till date, therefore, the expected completion date of the project, according to the contractor's latest statement, China National Building Materials Corporation (CNBM), is an additional 150 days from resuming work on the project site, after easing /lifting restrictions on international travel and the arrival of all technical team to the work site. Hence, the expected completion date for the project and the commercial operation is expected to be the fourth quarter of 2021. Due to the contractor's failure to adhere to the schedule and the current conditions causing suspension of travel due to spread of Corona virus (CoVid-19), the contractor was unable to complete the installations and commissioning work necessary for operation and testing of equipment by the original equipment manufacturers (OEMs) due to the absence of the contractor's team at the site project at the moment.