Centrais El tricas Brasileiras S/A signed the service provision contract which will allow the resumption of works on the Angra 3 Nuclear Power Plant, within the scope of the Critical Path Acceleration Plan between the subsidiary Eletrobras Termonuclear ("Eletronuclear") and the consortium formed by Ferreira Guedes, Matrix and ADtranz. Among the main measures included in the Critical Path Acceleration Plan is the completion of the concrete superstructure of the Angra 3 reactor building. In addition, an important part of the electromechanical assembly will be carried out, which includes the closing of the containment steel sphere and the installation of the used fuel pool, the polar bridge and the semi-gantry crane.

Subsequently, another bid will be held to hire the company or consortium that will complete the civil works and electromechanical assembly of the plant.