For personal use only

Market Update

Peko Project Progress Report

November 30th, 2021

  • Rail agreement executed with OneRail matching initial planned production volume from Peko Iron project utilising the existing intermodal service
  • Darwin port access and minerals storage lease contracts have been finalised for execution, providing certainty over product storage and handling prior to shipping
  • ICA Mining's creditors have all executed agreements to novate their debts, satisfying the agreement between Elmore and ICA Mining (ICA), securing the key plant equipment items and allowing ICA to be released from external Administration
  • Prefabricated structures and equipment is steadily arriving on site, with fabrication of all remaining items nearing completion and scheduled to be mobilised to site this week.
  • Key management personnel are on-site in preparation for plant construction and commissioning.
  • Completion of commissioning remains on schedule to be achieved prior to the end of the calendar year, with first train of magnetite for Darwin Port being planned for January 2022.

Elmore Ltd (ELE: ASX or Elmore) is pleased to provide an update on the development of the Peko Magnetite, Gold, Copper and Cobalt project in the Northern Territory.

For personal use only

Process plant with magnetite tailings stockpile in the background

Prefabricated skid mounted structure with fixed tower in preparation for process equipment to be installed

For personal use only

Background

Elmore has been contracted to deliver and operate a magnetite processing plant for the Peko Iron and Polymetallic Project ("Peko") located in the Tennant Creek region in the Northern Territory.

Elmore has now passed a number of major project milestones, having completed design and procurement of all plant and equipment and is in the process of execution of all of the major project contracts.

The Company is now within days of completion of all off-site components of the construction phase of the plant and has commenced moving the prefabricated plant components to site to tie together and complete commissioning. Some key equipment is being commissioned in Perth before being mobilised, whilst others will occur on site.

Commissioning of the plant is on schedule to be completed before Christmas and the Company is currently on schedule to commence hauling material from site to port soon after.

Key Logistics Contracts

An agreement has been executed with OneRail to provide haulage from Tennant Creek to Darwin Port utilising the intermodal rail service 5 days per week. The contract covers the initial targeted production level of 350,000 tonnes per annum of magnetite concentrate that is planned for Peko.

Port access and minerals storage shed contracts have been negotiated and ready for execution with Darwin Ports, providing the project the ability to stockpile product as it comes off the rail and then loaded onto ships once a suitable sized stockpile is achieved. Contract execution is on track to be completed this week.

Elmore has also secured a new Reach Stacker for handling the half-height sea containers on/off the trucks at Tennant Creek rail siding in preparation for being railed to Darwin, where the contents will then be tipped into the minerals shed.

The above agreements lock in the logistics capacity to meet Peko's planned production.

For personal use only

Linfox's Reach Stacker moving half-height sea containers in Tennant Creek similar to what will be

used by Peko to unload trucks

Creditor Novation

As previously announced, as part of the earn-in-agreement, Elmore has agreed to pay three nominated ICA's creditors $1,700,000 and waive $660,000 in management fees owing to Elmore.

These ICA creditors have all now entered into novation deeds which transfer their debts from ICA into a short-term fund agreement with Elmore, satisfying the agreement between Elmore and ICA. The key terms of the funding agreement are:

  • 6-monthterm
  • 10% interest rate
  • $1 per tonne royalty, pro-rata over a $6 million financing facility.
  • If the outstanding amounts are repaid by January 30th, 2022, no royalty is payable.

Post novation of the debts, the equipment valued at circa $3 million will transfer to Peko, and will allow Elmore to refinance these debts, rather than relying on those Creditors to act as funders.

The agreement with ICA states that the $2.36 million ($1.7 million to others and $660k to Elmore) will be repaid to Elmore before any distributions are made to project shareholders. This means that not including distribution of profit, based on 350,000 tonnes per annum

For personal use only

production rate and a 0.73 USD: AUD exchange rate, in the first 12 months Elmore will be

entitled to:

Management Fees:

$1,800,000

Royalties:

$ 958,904

Creditor Payments:

$2,360,000

Thus, the total first 12-monthminimum entitlements paymentsfrom the project, not including profit distributions, amounts to $5,118,904

The Company has forecast free cash flows to be greater than the above minimum entitlements.

Whilst the Company plans to re-finance these notes, the above minimum income, and the early rebating of the creditor payments, provides Elmore the comfort that the Company can repay the creditors in full within 6 months if alternative re-financing is not achieved.

Site Management

Key management personnel have mobilised to site in preparation for completion of construction and commissioning.

Mr Jason Young, Elmore's Head of Metallurgy will commence as the Acting Registered Manager. Mr Young has extensive experience with magnetite and other minerals having previously held senior positions at Fortescue Metals Group, Rio Tinto and the CSIRO Iron Ore Division. Mr Youngs focus will be to bring the plant to steady state and maximise the quality of the product produced.

Three 500kVA Diesel Generator Sets Preparing to leave Elmore's Malaga Workshop

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Elmore Limited published this content on 29 November 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 29 November 2021 21:30:13 UTC.