Farglory Land Development Co., Ltd. announced supplementary agreement to the JV contract, with land bank located in Linkou District, New Taipei City. Date of occurrence of the event: February 20, 2023. Counterparty to the contract and relationship with the Company: Transaction party: Tianlian Assets Co., Ltd. Relationship with company: No.

Major content of the contract (including total contract amount, anticipated monetary amount of participation in the investment, and start and end dates of the contract), restrictive covenants, and other important terms and conditions: Average slip ratio for overall JV contract, 41.58% to landlord, 58.42% to developer. Total estimated construction costs amount to TWD 0.8 billion.