ASX ANNOUNCEMENT
19 January 2022 | ASX: G1A |
ABRA CONSTRUCTION TO 39% COMPLETE
GALENA MINING LTD. ("Galena" or the "Company") (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine ("Abra" or the "Project") has reached 39% complete on 31 December 2021. Construction milestones achieved during the month include,
- Completion and commissioning of mines new airstrip (figure 1 below)
- Manufacture completion of primary jaw crusher (figure 2 below)
Managing Director, Tony James commented, "The completion and commissioning of the new Abra airstrip is a really significant milestone for the project. Being able to use larger planes for our FIFO work cycles during the remaining construction phase of the project makes a significant improvement to the project's logistics and accessibility. The overall construction progress at Abra has now reached 39% complete, with the focus remaining on the other key site construction activities.
Underground development has reached 440m from the portal against a plan of 364m."
Figure 1 - Completed new Abra airstrip commissioned in early January and now fully
operational.
GALENA MINING LTD.
CORPORATE OFFICE: GF, 1 CENTRO AVE, SUBIACO WA 6008 (TEL 08 6166 3750)
WEBSITE: www.galenamining.com.au/ TWITTER: @GalenaMiningASX
For personal use only
Figure 2 - Manufactured Abra primary Jaw Crusher assembly.
Update on Abra Project progress
Abra Construction Progress At 31 December 2021 (Percentage Spent By Category) | Remaining | |||||||||||||||||||||||
% Actual | % Planned | Project | ||||||||||||||||||||||
Capex | ||||||||||||||||||||||||
Accommodation Camp - $14.7M | 100% | $0.1M | ||||||||||||||||||||||
100% | ||||||||||||||||||||||||
Bulk Earthworks - $15.0M | 69% | $4.6M | ||||||||||||||||||||||
77% | ||||||||||||||||||||||||
Process Plant EPC - $81.9M | 26% | $60.4M | ||||||||||||||||||||||
26% | ||||||||||||||||||||||||
Non-Process Infrastructure - $6.0M | 54% | $2.8M | ||||||||||||||||||||||
56% | ||||||||||||||||||||||||
Mining Pre-Production - $48.2M | 29% | $34.3M | ||||||||||||||||||||||
26% | ||||||||||||||||||||||||
Other Pre-Production - $12.3M1 | 52% | $5.9M | ||||||||||||||||||||||
55% | ||||||||||||||||||||||||
Owner's Costs & Contingencies - $53.3M2 | 39% | $32.4M | ||||||||||||||||||||||
44% | ||||||||||||||||||||||||
Total Project Capex - $231.4M3 | 39% | $140.5M | ||||||||||||||||||||||
40% | ||||||||||||||||||||||||
0% | 10% | 20% | 30% | 40% | 50% | 60% | 70% | 80% | 90% | 100% |
Notes: (1) Includes water supply & recovery, vehicles & mobile equipment, initial fills & spare parts, shire road maintenance, paste fill plant acquisition and construction indirect costs. (2) Includes employee & contractor, flights, accommodation, fuel, site management and general & administration costs as well as additional owner's contingencies on the remaining project capex. (3) Total project capex includes expenditure from the commencement of the project in July 2019 through to planned practical completion of the process plant in January 2023. As at 31 December 2021 the total remaining project capex was $140.5M.
Figure 3 - Shows the progress of the various Abra construction packages.
Page 2
For personal use only
Description | Manufacturer | Source | Order | Completion | Forecast | ||||||||||
Country | Date | Date | On Site | ||||||||||||
Date | |||||||||||||||
Jaw Crushers | Metso Outotec | China | 19 Aug 21 | 10 Jan 22 | 21 Feb 22 | ||||||||||
Cone Crushers | Metso Outotec | Finland | 19 Aug 21 | 16 Mar 22 | 27 Apr 22 | ||||||||||
Flotation Cells | Metso Outotec | China | 18 Aug 21 | 01 Jul 22 | 12 Aug 22 | ||||||||||
Thickener | Metso Outotec | China | 18 Aug 21 | 16 Mar 22 | 27 Apr 22 | ||||||||||
Slurry Analyser | Metso Outotec | Finland | 18 Aug 21 | 10 Jan 22 | 21 Feb 22 | ||||||||||
Grinding Mill | CITIC HIC | China | 23 Jul 21 | 04 Apr 22 | 30 May 22 | ||||||||||
Filter | Ishigaki | Japan | 26 Jul 21 | 31 May 22 | 12 Jul 22 | ||||||||||
Regrind Mill | Glencore | Germany | 23 Sep 21 | 29 Jun 22 | 03 Aug 22 | ||||||||||
LNG Storage | AMG | China | 15 Jun 21 | 28 Apr 22 | 05 Jul 22 | ||||||||||
Tanks | Cryogenics | ||||||||||||||
Table 1 - Key equipment order and delivery schedule from overseas suppliers.
Figure 4 - Construction offices, mine administration, and mining contractor buildings in place. Completed plant site earthworks in the foreground and civil construction occurring in the background on site power station earthworks.
Page 3
For personal use only
Figure 5 - Underground decline has progressed 440m project to date against a plan of
364m.
Figure 6 - Concentrate thickener fabrication.
Page 4
For personal use only
Figure 7 - Processing plant site works showing crusher, screening, and ore storage
foundations.
The Board of Directors of Galena authorised this announcement for release to the market.
For further information contact:
Galena Mining Limited
Anthony (Tony) James
Managing Director
Page 5
This is an excerpt of the original content. To continue reading it, access the original document here.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Galena Mining Ltd. published this content on 18 January 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 18 January 2022 22:51:09 UTC.