23 December 2021
For personal use only
Woodlark Gold Project
Exploration and Development Update
Geopacific Resources Limited ('Geopacific' or 'the Company'; ASX: GPR) is pleased to provide a development and exploration update for the Woodlark Gold Project ('the Project').
Highlights
Exploration
- Results from the initial six holes from the recently commenced grade control RC drill campaign on Woodlark Island (ref ASX release 30 September 2021) have been received by the Company. This drilling campaign is being undertaken to refine ore zones in advance of mining and to provide certainty around early production.
- Drilling results include:
-
080KUL159 with 29 metres at 7.6 g/t Au: o 080KUL158 with 31 metres at 6.7 g/t Au; o 080KUL172 with 50 metres at 4.6 g/t Au;
o 080KUL173 with 44 metres at 4.7 g/t Au; and o 080KUL171 with 41 metres at 3.9 g/t Au.
While a further 18 holes (1,200 samples) are currently in the laboratory in Lae, Papua New Guinea pending assay, the initial results compare favorably with the resource model which has an average grade of 1.04 g/t Au1.
- The drilling campaign remains active on site with a 20,000 metre grade control and near pit extension drilling campaign underway and a second drill rig scheduled to commence drilling in early Q1 2022.
-
Post completion of the grade control drilling, the RC drill rig will move into exploration drilling with an anticipated 40,000 metres of exploration drilling budgeted in CY 2022:
o Exploration drilling will be focused on the significant near pit exploration potential previously inaccessible due to the proximity of community;
o All three planned open pits at the Woodlark Gold Project are open at depth and laterally; and
o The current pit shells are constrained by data and not economics and an extensive drilling campaign has the potential to add additional in-pit ounces, reduce strip ratio and increase the life-of-mine production.
Development
- Progress continues with the essential development work packages including the construction of the permanent camp, community relocation, engineering and the process plant ground preparation. Key updates include:
- Earthwork activities to prepare the CIL tanks foundations is progressing with the placement of geotextile and fill material (see Figure 1);
- Geotechnical drilling has been completed for the wharf validating the revised location (see Figure 2);
1.See ASX Release - 12 March 2018
1
For personal use only
- Earthworks completed for the permanent camp, with flat pack buildings scheduled for delivery to the island in early Q1 2022;
- GR Engineering Services engineering of the process plant over 70% complete; and
- Continued community relocation program with over 50% of buildings complete.
- Further to the ASX Announcement of 11 November 2021, the work program to review the Project Development Schedule and Cost Estimate is continuing. Key updates include:
- Consistent with the experiences being noted more broadly across the resources industry, cost increases continue to be observed for a number of key Project related activities;
- Additional internal resources with extensive project development experience have been secured to assist with the review of all development assumptions, work packages and cost drivers and a number of these individuals will then join the Project Execution Team;
- Tender documents are being released for the revised wharf solution and deep sea tailings line to firm up these cost components; and
- The Board plans to engage a third party technical reviewer to assess Management's proposed revisions to the Project execution plan and the resulting costs to complete.
Chief Executive Officer, Tim Richards commented
The initial grade control drill results are extremely pleasing and support our view that there remains significant upside potential at the Project both within the existing pits and more broadly across the mining lease. With the impending arrival of the second drill rig, the drilling campaign will begin focusing on defining near pit potential concurrent with development activities. These early results highlight the possible upside that exists to add further mineral resources, and eventually ore reserves with the potential to significantly enhance the metrics of the Project. I look forward to updating the market on our exploration and development activities in coming periods."
Development Activity
Figure 1: Engineered backfill of the CIL Boxcut
2
Figure 2: Wharf access road and Geotech drilling
For personal use only
Figure 3: Completed Community Housing
This announcement was authorised by the Board of Geopacific.
For further information, please visit www.geopacific.com.auor contact Mr Tim Richards, CEO.
Company details | Board & Management | Projects |
Geopacific Resources Limited | Ian Clyne Chairman | PAPUA NEW GUINEA |
ACN 003 208 393 | Ian Murray Non-Executive Director | Woodlark Island Gold |
ASX Code: GPR | Colin Gilligan Non-Executive Director | |
info@geopacific.com.au | Sir Charles Lepani Non-Executive Director | |
http://www.geopacific.com.au | Tim Richards Chief Executive Officer | |
T +61 8 6143 1820 | Matthew Smith CFO and Company Secretary | |
HEAD OFFICE | Mike Meintjes Company Secretary | |
Level 1, 278 Stirling Highway | ||
Claremont WA 6010. | ||
PO Box 439, Claremont WA 6910. | ||
3
Appendix A: Woodlark Project Significant Intercepts
only | North | East | RL | Dip/ | Total | Down-hole | ||||
Azimuth | Depth | Mineralised Intersection | ||||||||
Hole ID | From | To | Interval | Gold | ||||||
m | m | M | degrees | m | grade | |||||
m | m | m | g/t Au | |||||||
080KUL158 | 8995914 | 469116 | 85 | -60/270 | 57 | 8 | 39 | 31 | 6.72 | |
50 | 56 | 6 | 4.81 | |||||||
Including | 13 | 14 | 1 | 17.3 | ||||||
17 | 19 | 2 | 25.3 | |||||||
use | 25 | 26 | 1 | 35.7 | ||||||
52 | 56 | 4 | 6.57 | |||||||
080KUL159 | 8995910 | 469120 | 87 | -60/270 | 60 | 14 | 43 | 29 | 7.62 | |
45 | 49 | 4 | 1.87 | |||||||
Including | 14 | 15 | 1 | 87.7 | ||||||
21 | 22 | 1 | 18.6 | |||||||
080KUL171 | 8995925 | 469113 | 84 | -60/270 | 60 | 0 | 7 | 7 | 0.56 | |
personal | ||||||||||
13 | 54 | 41 | 3.90 | |||||||
Including | 23 | 24 | 1 | 37.7 | ||||||
27 | 28 | 1 | 10.2 | |||||||
36 | 37 | 1 | 22.9 | |||||||
40 | 41 | 1 | 13.7 | |||||||
080KUL172 | 8995925 | 469119 | 84 | -60/270 | 60 | 0 | 50 | 50 | 4.61 | |
Including | 13 | 14 | 1 | 22.3 | ||||||
20 | 21 | 1 | 10.9 | |||||||
29 | 30 | 1 | 10.1 | |||||||
31 | 35 | 4 | 25.2 | |||||||
080KUL173 | 8995924 | 469125 | 85 | -60/270 | 55 | 0 | 2 | 2 | 0.88 | |
11 | 55 | 44 | 4.66 | |||||||
Including | 11 | 13 | 2 | 11.6 | ||||||
22 | 25 | 3 | 19.2 | |||||||
For | 32 | 37 | 5 | 11.2 | ||||||
40 | 41 | 1 | 11.6 | |||||||
080KUL174 | 8995924 | 469131 | 85 | -60/270 | 37 | 0 | 2 | 2 | 2.86 | |
21 | 37 | 16 | 7.08 | |||||||
Including | 21 | 22 | 1 | 23.5 | ||||||
28 | 36 | 8 | 10.2 |
BSRC21026 | 8993602 | 473100 | 65 | -90/0 | 90 | No significant Results | ||||
BSRC21037 | 8993552 | 472975 | 64 | -90/0 | 30 | No significant Results | ||||
BSRC21036 | 8993552 | 472950 | 64 | -90/0 | 70 | 44 | 47 | 3 | 3.23 | |
Including | 46 | 47 | 1 | 8.53 | ||||||
4
Appendix B: JORC Code, 2012 Edition - Table 1
For personal use only
Section 1: Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
CRITERIA | JORC CODE EXPLANATION | COMMENTARY | |
Sampling | Nature and quality of sampling (e.g. cut channels, | Sampling was conducted using diamond drilling | |
techniques | random chips, or specific specialised industry | (DD) and Reverse Circulation Drilling (RC). | |
standard measurement tools appropriate to the | Sampling of the diamond drilling comprised half | ||
minerals under investigation, such as down hole | core samples taken based on lithological, | ||
gamma sondes, or handheld XRF instruments, etc.). | alteration, and mineralisation breaks observed in | ||
These examples should not be taken as limiting the | geological logging. Generally, sampling is at 1m | ||
broad meaning of sampling. | intervals. | ||
Include reference to measures taken to ensure | 1 in 50 samples is a duplicate sample, taken from | ||
sample representivity and the appropriate | quarter core. | ||
calibration of any measurement tools or systems | Core recovery is routinely recorded for each drill | ||
used. | run | ||
RC drilling samples were collected in 1m intervals | |||
from a cyclone and weighed. The entire sample is | |||
riffle split using a 75% / 25% splitter, yielding | |||
approximately 3kg sub split for assaying. The 75% | |||
split is stored in plastic sample bags and removed | |||
from site on the completion of the hole to a bag | |||
farm for future reference if required. | |||
The sample splitter is cleaned with compressed air | |||
and water if necessary to ensure no contamination | |||
between samples. | |||
1 in 50 samples is a duplicate sample, collected as a | |||
re-split of the residual sample material. | |||
All samples were submitted to ITS Pty Ltd PNG | |||
(Intertek Services Ltd) - operated sample | |||
preparation laboratory on site. | |||
Sample pulps were sent for fire assay gold at | |||
Intertek's Lae analytical laboratory with with four- | |||
acid multi-element analysis by ICPMS method at | |||
Intertek Genalysis Townsville analytical laboratory. | |||
Blank, duplicate, and standard samples were | |||
inserted at various intervals based on Geopacific's | |||
QAQC procedure to ensure sample representivity | |||
and repeatability of the sampling results. |
5
This is an excerpt of the original content. To continue reading it, access the original document here.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Geopacific Resources Ltd. published this content on 22 December 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 22 December 2021 23:06:05 UTC.