Giyani Metals Corp. provided a progress update on the construction of the K.Hill demonstration plant ("Demo Plant") in Johannesburg. Key plant components continue to be delivered to the Demo Plant site, including the ball mill, classification screens, filter presses, boiler, compressors and vessels.

The fully fabricated 15 meter ("m") tall crystallization unit is due for installation in the coming weeks. The Company recently hosted a site visit by several financial institutions to the Demo Plant. Demo Plant Update.

Throughout May, several key elements of the Demo Plant were delivered to the site, including the Ball mill, classification screens, four specialist filter presses, the product dryer and the boiler. Civil works at the Demo Plant facility are near completion to allow delivery and erection of the crystallization unit, which is fully fabricated and packed for transport along with all its ancillary equipment. As the crystallizer is a modular design, most of the internal equipment such as the vessels, piping and valves are integral to the structural units, facilitating rapid reassembly on site.

The crystallization unit stands at over 15 m tall and will allow the Demo Plant to produce up to 600 kg of dry high-purity manganese sulphate monohydrate ("HPMSM") crystals per day depending on feedstock characteristics. The scale of crystallization unit is a critical element of the Demo Plant design, which is tailored to produce HPMSM crystals meeting the rigorous product specification set by potential customers, as part of steady state operations. Recently, the Company and its specialist hydrometallurgical consultants, MET63 (Pty) Limited, hosted a select group of financial institutions at the Demo Plant site to review progress.