Tuesday, 24 May 2018

KANMANTOO PRIMARY CRUSHER REFURBISHED

Hillgrove Resources Limited (ABN 73 004 297 116) (ASX: HGO) ("Hillgrove") is pleased to advise that the repairs and refurbishment to its primary crusher were successfully completed Wednesday 23 May 2018.

The Company took the opportunity to bring forward other planned preventative maintenance, including a SAG Mill girth gear rotation. Undertaking this work will now reduce the quarterly scheduled shut down in July 2018 by three days.

The processing facility is now running at full capacity.

For more information contact:

Mr Steven McClare

Mr Paul Kiley

CEO & Managing Director

CFO and Company Secretary

Tel: +61 (0)8 7070 1698

Tel: +61 (0)8 7070 1698

IIII HILLGROVE RESOURCES LIMITED ACN 004 297 116

5-7 King William Road, Unley SA 5061, Australia

www.hillgroveresources.com T +61 8 7070 1698 F +61 8 8538 5255

Attachments

Disclaimer

Hillgrove Resources Limited published this content on 24 May 2018 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 24 May 2018 01:42:04 UTC