At the Bournezeau site (85),
In total, our teams poured 2,200 m3 of low-carbon concrete per day, inside an impressive 1.80 m slippery formwork.
Last July, our teams installed 24 petals of 15 tons each, prefabricated on site with concrete from H-UKR 0% clinker cement, to form the inverted cone of the installation.
Built entirely of Hoffmann Green Technologies concrete, this new unit, with a production capacity of 250,000 t of carbon-free 0 clinker cement, will be commissioned by the end of 2022. Ultimately, it will enable the production of all current and future
Congratulations to our 56 companions mobilized 7 days a week-24 hours a day on this exceptional site.