OPG Power Ventures PLC reported production results for the third quarter and nine months ended December 31, 2014 and for the month ended January 2015. For the quarter, the company reported total power generation of 484 million units against 518 million units for the same period a year ago. Power generation in the third quarter of fiscal 2015 was 7% lower than in the previous year following the effect of planned shutdowns. Average plant load factor (PLF) of 94% and average tariff of INR 5.71 in the third quarter of fiscal 2015.

For the nine months, the company reported total power generation of 1,387 million units against 1,360 million units for the same period a year ago.

Average load factors for the three units in January 2015 were above 90%.

Overall, the company expects an average PLF of approximately 90% for the fiscal year ending March 31, 2015 at the Chennai plant as a whole.