  • Polenergia launched its thirteenth wind farm. The Grabowo WF consists of 20 turbines with a total capacity of 44 MW
Polenergia launched its thirteenth wind farm. The Grabowo WF consists of 20 turbines with a total capacity of 44 MW
Polenergia launched the Grabowo Wind Farm. This is the Group's thirteenth onshore wind farm. The Grabowo WF consists of 20 turbines with a total capacity of 44 MW. The wind farm can supply over 60,000 households with green energy. The Grabowo WF is the third wind farm opened by Polenergia this year. Its launch means that the Group's production capacity from renewable sources has exceeded the 0.5 GW limit.
Your browser does not support the video tag.

Polenergia's thirteenth wind farm is located in Podlasie, in the Grabowo gmina. The estimated annual production of the farm is approximately 125 GWh, which corresponds to the annual electricity demand of over 60,000 households. The launch of the Grabowo WF means that Polenergia's green generation capacity from wind and photovoltaic farms increases to 530 MW..

Decarbonization of the Polish economy is one of Polenergia's most important missions. We implement it by completing subsequent investments at an express pace. The launch of the Grabowo Wind Farm means another 44 MW of green power that the Group is introducing into the Polish energy system. Grabowo is the third wind farm launched by Polenergia this year. This means that over the last twelve months we have released almost 180 MW stored in renewable energy sources.

Dr. Michał Michalski

President of the Management Board of Polenergia S.A

The Grabowo WF is the third wind farm opened by Polenergia in 2023. Recently, the Group launched the Piekło Wind Farm with a capacity of 13.2 MW in Wielkopolska, and in the first half of this year - the Dębsk Wind Farm located in Mazovia. The investment with a capacity of 121 MW is one of the largest wind farms in Poland.

The power of individual Vestas V110 wind turbines installed at the Grabowo Wind Farm is 2.2 MW. One turbine, working at full power, can produce the energy needed to drive an electric car up to 200 km in just a minute.

The windmill gondolas are mounted 125 meters above the ground. The length of the blades is 55 meters. The total height of each windmill, including the blades, is 180 meters.

The Grabowo WF project won the auction in December 2021. Its construction began in April 2022 and ended in September 2023 with obtaining a license to generate electricity.

In the near future, Polenergia also plans to launch the Strzelino Photovoltaic Farm. The solar power plant with a capacity of 45.2 MWp is located in the Słupsk gmina. The construction of the Strzelino PF is planned to be completed in the first half of 2024.

The supplier of turbines and the entity providing technical service for a period of 30 years from the date of commissioning of the Grabowo WF is Vestas.

The contractor for comprehensive construction works related to foundations for wind turbines, adaptation of access roads for oversized transport, modernization of existing roads, construction of service roads, assembly platforms, assembly and electrical works and necessary construction works for the GPO power station along with the MV cable network and the HV cable network was Electrum Concreo Sp. z o. o.

The Contract Engineer service during the investment implementation was provided by WSP Polska Sp. z o. o. The construction was monitored by specialists from BIOEKSPERT, responsible for environmental supervision.