Skanska has signed a contract with
The project consists of building and installing piping and machinery for the new wastewater treatment plant. The treatment plant will be an active sludge plant based on simultaneous precipitation, in which wastewater is treated mechanically, chemically, and biologically. Wastewater will be treated with more modern and efficient technology that will also allow to remove nitrogen from the water at a larger extent. The plant will serve
The construction is scheduled to start in the first quarter of 2022, and it is expected to be completed during the first quarter of 2026.
Skanska has been part of this wastewater treatment plant project since 2019 by carrying out extensive excavations for the wastewater treatment plant.
For further information please contact:
Markku Ihamäki, District Manager, Skanska Finland, +358 40 022 1898
Pilvimaari Heikkinen, Communications Manager, Skanska Finland, tel +358 40 519 4787
Andreas Joons, Press Officer,
Direct line for media, tel +46 (0)10 448 88 99
This and previous releases can also be found atwww.skanska.com.
https://news.cision.com/skanska/r/skanska-builds-and-installs-piping-and-machinery-for-wastewater-plant-in-tampere--finland--for-eur-4,c3474039
https://mb.cision.com/Main/95/3474039/1511212.pdf
https://news.cision.com/skanska/i/image-20211217---image-credit-tampere-region-central-wastewater-treatment-plant,c2993540
(c) 2021 Cision. All rights reserved., source