Uniper's Staudinger 5 hard-coal-fired power plant ( 510 MW net) will 2023 cease commercial electricity production and be decommissioned by 21 May at the latest. This is the timetable set out in the Act to Reduce and End Coal-fired Power Generation of 13 August 2020 for those power plants that have been awarded a contract by the German Federal Network Agency in the fourth tender of 1 October 2021. The result of the auction was announced by the Federal Network Agency today. According to this, Staudinger 5 was one of three power plants to be awarded a contract - for 510 MW. A total of 533 MW were awarded in the auction.

This means that Uniper has now been successful in each of the Federal Network Agency's four auctions to date: The positive decisions for Heyden 4 power station (1st auction: 875 MW), Wilhelmshaven 1 (second auction: 757 MW), Scholven C (3rd auction: 345 MW) and now Staudinger 5 alone will enable Uniper to remove a total of 2.487 MW (net) of hard-coal capacity from the market ahead of schedule. In the case of Staudinger 5, the transmission system operator and the Federal Network Agency will also examine the power plant's potential system relevance.

The Staudinger power plant in Großkrotzenburg is one of Uniper's most powerful power plant sites and the largest conventional power plant in the state of Hessen. Currently, only Uniper's hard-coal-fired unit 5 is used on the electricity market. The natural gas-fired Block 4 (622 MW) is held in reserve by the grid operator TenneT for grid stabilisation and as reserve capacity. In addition, the city of Hanau and the local municipality are supplied with district heating by the power plant.

David Bryson, Uniper's COO: "We're not only on track to phase out coal-fired generation, we're wellahead of our own announcements. This shows that we are serious about a rapid phase-out. Staudinger power station is located at one of the most important hubs of the German power grid and is an important element for us in the "Making Net Zero Possible" project. Our remaining unit 4 is gas-fired and continues to fulfil a central function for security of supply in Germany.

However, commercial coal-fired power generation will come to an end at this site next May 22, 2023. Together with our partners, Stadtwerke Hanau and Gemeindewerke Großkrotzenburg, we will secure our contractual obligations to supply district heating by other means. Our focus is above all on preserving as many jobs as possible through a consistent realignment of the site."

In January 2020, Uniper presented a decommissioning plan for its hard-coal-fired power plants in Germany, which is intended to achieve CO2 savings of up to approximately 18 million metric tons of CO2 per year. The plan calls for the decommissioning of hard-coal-fired power stations with a total capacity of about 2,900 MW by the end of 2025 at the latest.

The German Federal Network Agency issues invitations to tender on fixed dates for the decommissioning of hard coal-fired assets by 2026. Participants in the auction offer to decommission a power plant on the date defined in the tender in return for payment of the bid value submitted by them. In the first auction, which started on September 1, 2020, a capacity of four gigawatts (GW) was tendered; in the second auction on January 4, 2021, 1.5 GW were tendered; in the third, around 2.5 GW and in the fourth, 433 MW.