Valaris Limited
Fleet Status Report
October 27, 2021
New Contracts and Extensions, Rig Sales and Other Updates Since Last Fleet Status Report
Floaters
•VALARIS DS-9 awarded a two-year contract with ExxonMobil offshore Angola. The contract is expected to commence in June 2022.
•VALARIS DS-4 awarded a contract with Petrobras offshore Brazil. The contract is for a minimum term of 548 days and is expected to commence by early second quarter 2022.
•VALARIS DS-10 awarded two 1-well contracts with Shell offshore Namibia and Sao Tome and Principe, respectively. The first of these two contracts is expected to commence in November 2021. The Sao Tome and Principe contract will follow on directly from the Namibia contract. The contracts have an estimated duration of 60 days each.
•VALARIS MS-1 awarded a four-well P&A contract with Eni offshore Australia. The contract is expected to commence in November 2021 with an estimated duration of 90 days.
Jackups
•VALARIS 36 bareboat charter agreement with ARO Drilling extended by 211 days from September 2021 to March 2022. ARO Drilling's contract with Saudi Aramco has been extended for the same period.
•VALARIS 123 awarded a contract with TAQA offshore the Netherlands. The contract is expected to commence in November 2021 with an estimated minimum duration of 60 days.
•VALARIS 123 awarded a one-well contract with Cairn Energy in the UK North Sea. The contract is expected to commence in the second quarter of 2022 with an estimated duration of 72 days.
•VALARIS 107 awarded a one-well contract with Carnarvon Petroleum offshore Timor-Leste. The contract is expected to commence in November 2021 with an estimated duration of 30 days.
•VALARIS 107 awarded a two-well contract with Vermilion Oil & Gas offshore Australia. The contract is expected to commence in April 2022 with an estimated duration of 60 days.
•VALARIS 144 awarded a 30-day contract with an undisclosed operator in the U.S. Gulf of Mexico. The contract is expected to commence late in the fourth quarter of 2021 or early in the first quarter of 2022.
•VALARIS Norway awarded a contract for accommodation work with Harbour Energy in the UK North Sea. The contract is expected to commence in November 2021.
Rig Sales
•VALARIS 22 and 100 have been sold and retired from the offshore drilling fleet.
•VALARIS 142 has been sold to an operator and can only be utilized on specific assets.
Other
•VALARIS 8503, 8505 and 8506 have been renamed VALARIS DPS-3, DPS-5 and DPS-6, respectively, in the Fleet Status Report.
•VALARIS JU-290, JU-291 and JU-292 have been renamed VALARIS Viking, Stavanger and Norway, respectively, in the Fleet Status Report.
•VALARIS JU-250 has been renamed VALARIS 250 in the Fleet Status Report. This naming convention applies to all Valaris jackups, except for VALARIS Viking, Stavanger and Norway.

New Disclosure: bolded text signifies contracts and extensions that have not been previously disclosed
Page 1 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Contract Backlog(1) (2)
($ millions)
2021 2022 2023 2024+ Total
Contracted Days(1) (2)
2021 2022 2023 2024+
Drillships $ 46.5 $ 398.6 $ 306.2 $ 587.3 $ 1,338.6 Drillships 239 1,885 1,369 1,917
Semisubmersibles 18.7 111.8 132.8 14.6 277.9 Semisubmersibles 126 569 602 65
Floaters $ 65.2 $ 510.4 $ 439.0 $ 601.9 $ 1,616.5 Floaters 365 2,454 1,971 1,982
HD - Ultra-Harsh & Harsh $ 52.5 $ 213.9 $ 41.2 $ - $ 307.6 HD - Ultra-Harsh & Harsh 533 1,993 435 -
HD & SD - Modern 42.0 158.1 53.9 20.5 274.5 HD & SD - Modern 581 2,202 708 304
SD - Legacy 13.2 68.7 3.6 - 85.5 SD - Legacy 195 980 55 -
Jackups $ 107.7 $ 440.7 $ 98.7 $ 20.5 $ 667.6 Jackups 1,309 5,175 1,198 304
Other(3)
$ 22.8 $ 11.1 $ - $ - $ 33.9
Other(3)
573 678 - -
Total $ 195.7 $ 962.2 $ 537.7 $ 622.4 $ 2,318.0 Total 2,247 8,307 3,169 2,286
ARO Drilling(4)
Average Day Rates(1) (2)
2021 2022 2023 2024+
Owned Rigs $ 46.3 $ 173.6 $ 173.6 $ 363.9 $ 757.4 Drillships $ 195,000 $ 211,000 $ 224,000 $ 306,000
Leased Rigs 40.6 48.1 - - 88.7 Semisubmersibles 148,000 196,000 221,000 225,000
Total $ 86.9 $ 221.7 $ 173.6 $ 363.9 $ 846.1 Floaters $ 179,000 $ 208,000 $ 223,000 $ 304,000
Valaris 50% Share of ARO Owned Rigs $ 23.2 $ 86.8 $ 86.8 $ 181.9 $ 378.7 HD - Ultra-Harsh & Harsh $ 98,000 $ 107,000 $ 95,000 $ -
Adjusted Total(5)
$ 218.9 $ 1,049.0 $ 624.5 $ 804.3 $ 2,696.7 HD & SD - Modern 72,000 72,000 76,000 68,000
SD - Legacy 68,000 70,000 65,000 -
(1) Contract backlog, contracted days and average day rates as of October 27, 2021.
(2) Contract backlog and average day rates exclude certain types of non-recurring revenues such as lump sum mobilization payments. Contract backlog and contracted days include backlog and days when a rig is under suspension. Contract backlog includes drilling contracts subject to final investment decision (FID) and drilling contracts which grant the customer termination rights if FID is not received with respect to projects for which the drilling rig is contracted. Average day rates are adjusted to exclude suspension backlog and days.
(3) Other represents contract backlog and contracted days related to bareboat charter agreements and management services contracts.
(4) ARO Drilling contract backlog as of October 27, 2021.
(5) Adjusted total is Valaris consolidated total plus Valaris 50% share of ARO owned rigs.
Jackups $ 82,000 $ 85,000 $ 82,000 $ 68,000
HD = Heavy Duty; SD = Standard Duty
Page 2 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Year Delivered Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Drillships
VALARIS DS-18 GustoMSC P10000 2015 Chevron
Chevron
U.S. GOM
U.S. GOM
Aug 20
Jan 22
Jan 22
Jan 25
VALARIS DS-16

GustoMSC P10000 2014 Occidental U.S. GOM May 22 Apr 24 Rig currently in Spain being reactivated
VALARIS DS-15 GustoMSC P10000 2014 TotalEnergies Brazil Jun 21 Aug 22
VALARIS DS-12
DSME 12000 2014 TotalEnergies
BP
BP
Ivory Coast
Angola
Mauritania / Senegal
Jul 21
Sep 21
Feb 22
Aug 21
Jan 22
Nov 22
VALARIS DS-10
Samsung GF12000 2017
TotalEnergies
Shell
Shell

Shell
Nigeria
Namibia
Sao Tome & Principe
Nigeria
Jul 21
Nov 21
Feb 22

Apr 22

Nov 21
Jan 22
Apr 22

Oct 22
Stacked
VALARIS DS-17 GustoMSC P10000 2014 Stacked Spain
VALARIS DS-11 DSME 12000 2013 TotalEnergies U.S. GOM Jul 24 Dec 27 Rig currently stacked in Spain. The contract contains early termination provisions should the project not receive a final investment decision (FID) by the customer
VALARIS DS-9
Samsung GF12000 2015 ExxonMobil Angola Jun 22 May 24 Rig currently stacked in Spain
VALARIS DS-8
Samsung GF12000 2015 Stacked UK
VALARIS DS-7
Samsung 96K 2013 Stacked Spain
VALARIS DS-4 Samsung 96K 2010 Petrobras Brazil Apr 22 Oct 23 Rig currently in transit from UK to Spain where it will be reactivated
Purchase Options(2)
VALARIS DS-14

DSME 12000 Under Construction South Korea Option to take delivery by year-end 2023. Purchase price of approx. $218 million assuming a Dec 31, 2023 delivery
VALARIS DS-13

DSME 12000 Under Construction South Korea Option to take delivery by year-end 2023. Purchase price of approx. $119 million assuming a Dec 31, 2023 delivery
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 3 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Year Delivered Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Semisubmersibles
VALARIS DPS-5

ENSCO 8500 Series,
DP + Moored
2012 Lukoil
Eni
Mexico
Mexico
Jul 21
Oct 21
Oct 21
Dec 21
VALARIS DPS-1

F&G ExD Millennium, DP 2012 Woodside
Woodside
Australia
Australia
Mar 22
Jan 23
Jan 23
Mar 24
Rig currently warm stacked in Malaysia
The January 2023 contract is subject to final investment decision (FID) by the customer
VALARIS MS-1

F&G ExD Millennium, Moored 2011
Santos
Eni
Santos
Santos
Australia
Australia
Australia
Australia
May 21
Nov 21
May 22
Jun 22
Oct 21
Feb 22
May 22
Aug 23
Stacked
VALARIS DPS-6
ENSCO 8500 Series, DP 2012 Stacked U.S. GOM
VALARIS DPS-3
ENSCO 8500 Series,
DP + Moored
2010 Stacked U.S. GOM
Changes: bolded rig names and underlined text signify changes in rig status from previous report

Page 4 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Year Delivered Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Jackups
Heavy Duty Ultra-Harsh Environment(3)
VALARIS Norway KFELS N Class 2011
ConocoPhillips
Harbour Energy

Norway
UK

Nov 19
Nov 21

Aug 21
Jan 22

Accommodation work
VALARIS Stavanger KFELS N Class 2011 Equinor Norway Oct 19 May 22
VALARIS Viking KFELS N Class 2010 Lundin
Spirit
Repsol
Norway
Norway
Norway
May 20
Oct 21
May 22
Oct 21
Nov 21
Oct 22


Repsol contract could be performed by VALARIS Viking or VALARIS Stavanger
VALARIS 250 LT Super Gorilla XL 2003 Saudi Aramco Saudi Arabia Jun 18 Dec 21
Leased to ARO Drilling(4)
VALARIS 249 LT Super Gorilla 2002 OMV New Zealand Jan 22 Feb 23 Rig currently mobilizing to New Zealand
VALARIS 248 LT Super Gorilla 2000 Neptune UK Aug 20 Aug 22
VALARIS 247 LT Super Gorilla 1998 DNO UK May 21 Aug 22
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 5 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Year Delivered Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Jackups
Heavy Duty Harsh Environment(3)
VALARIS 123 KFELS Super A 2019
Harbour Energy
TAQA
Cairn Energy
UK
Netherlands
UK
Oct 20
Nov 21
Apr 22
Oct 21
Jan 22
Jun 22
VALARIS 122

KFELS Super A 2014 Shell UK Jan 20 May 22
VALARIS 121 KFELS Super A 2013 Harbour Energy UK Jul 21 Jul 23
VALARIS 120 KFELS Super A 2013 Harbour Energy UK Jul 17 Jul 23
Stacked
VALARIS 102 KFELS MOD V-A 2002 Stacked U.S. GOM
Changes: bolded rig names and underlined text signify changes in rig status from previous report

Page 6 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Year Delivered Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Jackups
Heavy Duty - Modern(3)
VALARIS 118 LT 240-C 2011 Fieldwood Mexico Mar 20 Mar 22
VALARIS 117 LT 240-C 2009 Eni Mexico Oct 21 Oct 23
VALARIS 116 LT 240-C 2008 Saudi Aramco Saudi Arabia Dec 18 Dec 21
Leased to ARO Drilling(4)
VALARIS 115 BM Pacific Class 400 2013 Mubadala Petroleum
Mubadala Petroleum
Thailand
Thailand
Feb 21
Feb 22
Nov 21
Sep 22
VALARIS 110 KFELS MOD V-B 2015 North Oil Company
North Oil Company
Qatar
Qatar
Sep 17
Oct 21
Sep 21
Oct 24
VALARIS 108 KFELS MOD V-B 2007 Saudi Aramco Saudi Arabia Nov 18 Nov 22
VALARIS 107 KFELS MOD V-B 2006
Jadestone
Carnarvon Petroleum
Vermilion Oil & Gas
Australia
Timor-Leste
Australia
Jun 21
Nov 21
Apr 22
Nov 21
Dec 21
Jun 22
VALARIS 106 KFELS MOD V-B 2005 BP Indonesia Jan 18 Jan 23
Stacked
VALARIS 114 BM Pacific Class 400 2012 Stacked
Philippines
VALARIS 113 BM Pacific Class 400 2012 Stacked Philippines
VALARIS 111 KFELS MOD V-B 2003 Stacked Croatia
VALARIS 109 KFELS MOD V-Super B 2008 Stacked Namibia
VALARIS 104 KFELS MOD V-B 2002 Stacked UAE
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 7 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Year Delivered Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Jackups
Standard Duty - Modern
VALARIS 148 LT Super 116-E 2013 Saudi Aramco Saudi Arabia Nov 19 Nov 22
Leased to ARO Drilling(4)
VALARIS 147 LT Super 116-E 2013 Saudi Aramco Saudi Arabia Sep 19 Aug 22
Leased to ARO Drilling(4)
VALARIS 146 LT Super 116-E 2011 Saudi Aramco Saudi Arabia Sep 18 Dec 21
Leased to ARO Drilling(4)
VALARIS 144 LT Super 116-E 2010
Fieldwood
W&T Offshore
Undisclosed Operator
Mexico
U.S. GOM
U.S. GOM
May 20
Nov 21
Dec 21

Oct 21
Dec 21
Jan 22

Contract transferred from VALARIS JU-117
VALARIS 143 LT Super 116-E 2010 Saudi Aramco Saudi Arabia Oct 18 Dec 21
Leased to ARO Drilling(4). Contract between ARO Drilling and customer suspended from May 21 to Jul 21 for suspension and maintenance period, then returned to operating day rate in Aug 21
VALARIS 141 LT Super 116-E 2016 Saudi Aramco Saudi Arabia Aug 18 Feb 22
VALARIS 140
LT Super 116-E 2016
Saudi Aramco

Saudi Arabia

Jul 18

Dec 21
VALARIS 76
LT Super 116-C 2000 Saudi Aramco Saudi Arabia Jan 15 Apr 23
Contract suspended from Sep 20 to Sep 21, then returned to operating day rate
Stacked
VALARIS 145 LT Super 116-E 2010 Stacked

U.S. GOM
VALARIS 75 LT Super 116-C 1999 Stacked U.S. GOM
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 8 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Year Delivered Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Jackups
Standard Duty - Legacy
VALARIS 92 LT 116-C 1982 Harbour Energy UK Feb 17 Dec 22
VALARIS 72 Hitachi K1025N 1981 Eni
UK
Jan 20

Jan 23
VALARIS 54 F&G L-780 Mod II-C 1982 Saudi Aramco Saudi Arabia Sep 14 Sep 22 Contract suspended from Oct 21 to Dec 21, then expected to return to operating day rate until end of contract
VALARIS 36 LT 116-C 1981 Saudi Aramco Saudi Arabia Sep 18 Mar 22
Leased to ARO Drilling(4)
Stacked
VALARIS 67 LT 84-CE 1976 Stacked Indonesia
VALARIS 37 LT 116-C 1981 Stacked Bahrain Upon completion of its contract with ARO Drilling in Oct 21, the rig was returned to Valaris and stacked
Sold / Held for Sale
VALARIS 142 LT Super 116-E 2008 Sold
VALARIS 100 LT Gorilla 1987 Sold
VALARIS 22 LT 116-C 1980 Sold
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 9 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Asset Category / Rig Design Customer/
Status
Location Contract Start Date
Contract End Date(1)
Comments
Other
Drilling Management
Thunder Horse Deepwater Semisubmersible BP U.S. GOM Jan 17 Jan 22
Mad Dog Deepwater Spar Drilling Rig BP U.S. GOM Jan 17 Jan 22 On a standby rate from Apr 20 to Oct 21, and then return to operating day rate until end of contract
ARO Drilling
Jackup Rigs Owned by ARO Drilling
ARO 2001 LT 116-C Saudi Aramco Saudi Arabia Oct 17 Jan 26
ARO 2003 BM 200-H Saudi Aramco Saudi Arabia Feb 18 Feb 26
ARO 3001 LT Tarzan 225-C Saudi Aramco Saudi Arabia Oct 17 Jan 26
ARO 3002 LT Tarzan 225-C Saudi Aramco Saudi Arabia Oct 17 Jan 26
ARO 3003 LT Tarzan 225-C Saudi Aramco Saudi Arabia Oct 18 Dec 21
ARO 3004 LT Tarzan 225-C Saudi Aramco Saudi Arabia Oct 18 Dec 21
ARO 4001 KFELS Super B Saudi Aramco Saudi Arabia Oct 17 Jan 26
ARO 2005 LT 116-C Under Construction Saudi Arabia Delivery expected in 2022
ARO 2006 LT 116-C Under Construction Saudi Arabia Delivery expected in 2022
Changes: bolded rig names and underlined text signify changes in rig status from previous report

(1) Contract duration does not include any unexercised optional extensions. Contract end dates can vary based on how long it takes to complete the wells subject to the contract.
(2) Valaris has the right, but not the obligation, to take delivery of either or both rigs on or before December 31, 2023. Not included in Valaris' fleet count.
(3) Heavy duty jackups are well-suited for operations in tropical revolving storm areas.
(4) Rigs leased to ARO Drilling via bareboat charter agreements to fulfill contracts between ARO Drilling and Saudi Aramco.
Page 10 of 12

Page 11 of 12

Valaris Limited
Fleet Status Report
October 27, 2021
Additional Information Regarding this Fleet Status Report
Day Rate and Terms. The day rates reflected in this Fleet Status Report are stated in U.S. dollars and are the operating day rates charged to customers, which may include estimated contractual adjustments for changes in operating costs and/or reimbursable cost adjustments for ongoing expenses such as crew, catering, insurance and taxes. The day rates, however, do not include certain types of non-recurring revenues such as lump sum mobilization payments, revenues earned during mobilizations, revenues associated with contract preparation and other non-recurring reimbursable items such as mobilizations and capital enhancements, and the impact of the fair market value adjustments to previously acquired drilling contracts. Routine and non-routine downtime may reduce the actual revenues recognized during the contract term. Additionally, we sometimes negotiate special rates and/or day rate adjustments with customers that may reduce revenues recognized.
Forward Looking Statements. Statements contained in this Fleet Status Report that are not historical facts are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Forward-looking statements include words or phrases such as "anticipate," "believe," "estimate," "expect," "intend," "plan," "project," "could," "may," "might," "should," "will" and similar words and specifically include statements involving future rig day rates including adjustments with the customer; future levels of offshore drilling activity; discussions with the customer; backlog; cost adjustments; utilization; estimated rig availability; expected work commitments and contracts; contract duration, status, terms and other contract commitments; letters of intent, letters of award or other correspondence indicating an award; rig enhancement projects; new rig commitments; the expected period of time and number of rigs that will be in a shipyard for repairs, maintenance, enhancement or construction; sale leaseback transactions; scheduled delivery dates for rigs; performance of our joint venture with Saudi Aramco; the timing of delivery, mobilization, contract commencement, relocation or other movement of rigs; and our intent to sell or scrap rigs. Such statements are subject to numerous risks, uncertainties and assumptions that may cause actual results to vary materially from those indicated, including the effects of the chapter 11 cases on the Company's business, relationships, comparability of our financial results, ability to access financing sources, the COVID-19 outbreak and global pandemic, the related public health measures implemented by governments worldwide, which may, among other things, impact our ability to staff rigs and rotate crews; cancellation, suspension, renegotiation or termination of drilling contracts and programs including drilling contracts which grant the customer termination rights if final investment decision (FID) is not received with respect to projects for which the drilling rig is contracted; potential additional asset impairments; our failure to satisfy our debt obligations; our ability to obtain financing, service our debt, fund negative cash flow and capital expenditures and pursue other business opportunities; adequacy of sources of liquidity for us and our customers; actions by regulatory authorities, rating agencies or other third parties; actions by our security holders; availability and terms of any financing; commodity price fluctuations, customer demand, new rig supply, downtime and other risks associated with offshore rig operations; severe weather or hurricanes; changes in worldwide rig supply and demand, competition and technology; future levels of offshore drilling activity; governmental action, civil unrest and political and economic 3 uncertainties; terrorism, piracy and military action; risks inherent to shipyard rig construction, repair, maintenance or enhancement; our ability to enter into, and the terms of, future drilling contracts; the cancellation of letters of intent or letters of award or any failure to execute definitive contracts following announcements of letters of intent, letters of award or other expected work commitments; the outcome of litigation, legal proceedings, investigations or other claims or contract disputes; governmental regulatory, legislative and permitting requirements affecting drilling operations; our ability to attract and retain skilled personnel on commercially reasonable terms; environmental or other liabilities, risks or losses; debt restrictions that may limit our liquidity and flexibility; and cybersecurity risks and threats. In particular, the unprecedented nature of the current economic downturn, pandemic, and industry decline may make it particularly difficult to identify risks or predict the degree to which identified risks will impact the Company's business and financial condition. In addition to the numerous factors described above, you should also carefully read and consider "Item 1A. Risk Factors" in Part I and "Item 7. Management's Discussion and Analysis of Financial Condition and Results of Operations" in Part II of our most recent annual report on Form 10-K, as updated in our subsequent quarterly reports on Form 10-Q, which are available on the SEC's website at www.sec.gov or on the Investor Relations section of our website at www.valaris.com. Each forward-looking statement contained herein speaks only as of the date of this Fleet Status Report, and we undertake no obligation to publicly update or revise any forward looking statements, except as required by law.
Page 12 of 12