QUARTERLY REPORT

22 October 2019

September 2019 Quarter Production Report

Highlights

  • Safety performance improved with the TRIFR at 5.14 for the twelve months ended September
  • September quarter of 4.4Mt ROM coal production, up 22% on the previous corresponding period (pcp)
  • September quarter saleable coal production of 4.9Mt, up 23% on pcp
  • September quarter coal sales of 5.5Mt, up 14% on pcp
  • Whitehaven executed an agreement with EDF to acquire EDF's 7.5% interest in the Narrabri underground longwall mine which when completed will increase Whitehaven's equity ownership level to 77.5%
  • Equipment at Tarrawonga arriving and ramp up to 3Mtpa has commenced
  • Rehabilitation has commenced at Rocglen
  • FY20 guidance remains unchanged since issued to the market on 15 August 2019

Comments from the MD and CEO Paul Flynn

"It is pleasing to report that safety performance continues to improve, indicating that our efforts to further embed a safety-focused culture as production increases is bearing fruit."

"The quarter represents a solid planned start to the year, which will be second half weighted."

"Our program of improving efficiency continues, with the autonomous haulage evaluation program at Maules Creek entering the final stage of technical testing and commissioning in Q2 FY20. Further, new higher capacity longwall chock legs have started to arrive at Narrabri, ahead of the changeout later this year when we will install higher capacity cylinders to help build resilience against cyclical weighting events."

"Our inaugural Investor Day was well supported and will be a recurring feature in the company's investor relations calendar."

Safety

The safety outcome for the Group improved significantly in the September quarter with the TRIFR falling from 6.16 at the end of June to 5.14 at the end of September. Group TRIFR remains well below the NSW coal mining average of 14.64.

Whitehaven Managed Totals

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

Managed ROM Coal Production

4,420

3,619

22%

4,420

3,619

22%

Managed Saleable Coal Production

4,909

3,981

23%

4,909

3,981

23%

Managed Total Coal Sales

5,546

4,853

14%

5,546

4,853

14%

Whitehaven Coal Limited ABN 68 124 425 396

Level 28, 259 George Street, Sydney NSW 2000 | 02 8222 1100 | info@whitehavencoal.com.au | www.whitehavencoal.com.au

Whitehaven Equity Totals

Quarter Ended

Year to Date

Thousands of tonnes (including Sunnyside)

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

Equity ROM Coal Production

3,391

2,887

17%

3,391

2,887

17%

Equity Saleable Coal Production

3,861

3,267

18%

3,861

3,267

18%

Equity Sales of Produced Coal

4,030

3,649

10%

4,030

3,649

10%

Sales of Purchased Coal

436

406

7%

436

406

7%

Total Equity Coal Sales

4,466

4,055

10%

4,466

4,055

10%

Equity Coal Stocks at period end

1,606

1,446

11%

1,606

1,446

11%

Equity Coal Sales and Realised Pricing

Quarter Ended

Sep 2019

Jun 2019

Mar 2019

Dec 2018

Sep 2018

Total Equity Coal Sales

Mt

4.5

4.4

4.9

4.3

4.1

Sales of purchased coal (thermal)

Mt

0.4

0.4

0.5

0.4

0.4

Sunnyside

Mt

0.1

0.1

0.1

0.1

0.1

Equity Own Coal Sales

Mt

3.9

3.9

4.2

3.8

3.5

Coal sales mix (own coal sales)

High CV Thermal Coal

%

65%

65%

60%

69%

60%

Other thermal coal

%

15%

15%

14%

11%

20%

Metallurgical coal

%

20%

20%

26%

20%

20%

Pricing

NEWC Index

US$/t

68

80

96

104

118

JSM Quarterly (SSCC)

US$/t

115

129

132

135

129

Average SSCC spot price

US$/t

86

95

117

122

125

Price achieved (own coal sales)

Thermal coal

US$/t

73

84

97

108

113

Metallurgical coal

US$/t

100

107

120

122

128

Premium/Discount

Thermal to NEWC Index

%

7%

5%

1%

3%

(4%)

Metallurgical to JSM Qtrly

%

(13%)

(17%)

(9%)

(10%)

(1%)

Metallurgical to Spot Price

%

16%

12%

3%

0%

2%

Note: Figures may not add due to rounding

Equity coal sales for the September quarter, including purchased coal, were 4.5 Mt, 10% above the pcp. This sales volume improvement is reflective of the Narrabri production uplift when compared to the pcp, which was impacted by the move to LW107. Equity sales were higher than saleable production for the quarter as a result of drawing down stocks that were built up towards the end of FY19.

The globalCoal Newcastle Index (gC Newc) thermal coal price softened to average US$68/t for the quarter compared with the average price for Q4 FY19 of US$80/t. Whitehaven continues to experience solid end user demand for its high quality thermal coals.

In the September quarter, Whitehaven achieved an average realised price of US$73/t for thermal coal sales, 7% higher than the average gC Newc price for the period. Maules Creek achieved a premium of 17% above the gC Newc index price for its sales of thermal coal in the September quarter, reflecting a greater contribution of fixed quality premiums in the current price environment.

September quarter metallurgical benchmark prices (which use backward-looking 3 monthly average indices) were US$178/t for prime hard coking coal and US$115/t for SSCC.

2

Maules Creek Open Cut Mine

Whitehaven 75%

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

ROM Coal Production

1,962

2,268

(14%)

1,962

2,268

(14%)

Saleable Coal Production

2,034

1,980

3%

2,034

1,980

3%

Sales of Produced Coal

2,125

2,154

(1%)

2,125

2,154

(1%)

Coal Stocks at period end

441

476

(7%)

441

476

(7%)

As outlined at the Investor Day in September the focus of Maules Creek's current phase of the mine plan is on reaching the bottom of the pit to allow for in-pit dumping and the development of the south west area of the pit. The development of the south west area will expose more of the Braymont seam which is scheduled to be accessed in the second half of FY20.

Saleable coal production in the September quarter was higher than ROM coal production reflecting the draw-down of higher opening stock levels to support customer demand.

Managed metallurgical coal sales of 0.362Mt in the September quarter represented 17% of the total sales from the mine. For the comparative period in FY19 metallurgical coals sales were 0.601Mt, 27% of total sales, when the Braymont seam was accessed.

The autonomous haulage system (AHS) evaluation program at Maules Creek is progressing well. The final stage of technical testing and commissioning is being undertaken in Q2 FY20. The first AHS fleet, comprising 6 Hitachi EH5000 haulage trucks, is due to be placed into the mine's production area following completion of this stage of testing.

Narrabri Underground Longwall Mine

Whitehaven 70%

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

ROM Coal Production

1,793

550

226%

1,793

550

226%

Saleable Coal Production

1,800

729

147%

1,800

729

147%

Sales of Produced Coal

1,835

875

110%

1,835

875

110%

Coal Stocks at period end

949

258

268%

949

258

268%

Q1 FY20 production performance was in line with the mine plan. The significant increase in ROM, saleable coal production and sales of produced coal over the comparative period reflects good production levels at the mine for the quarter and pcp production being adversely impacted by the scheduled long wall changeout from LW107 to LW108.

Saleable coal production for the quarter was above ROM production as high opening coal stocks were draw down to support strong sales demand.

Sales of produced coal of 1.835Mt reflect strong production performance and the processing of high opening ROM stocks.

Coal stocks at the end of the quarter were larger than the comparative period because in the comparative period stocks had been drawn down as a result of the scheduled long wall changeout from LW107 to LW108.

Roadway development, including cut and flit on the Southern side of the Mains, was 7.2 kilometres for the quarter. The level of Mains development for the quarter is in-line with Narrabri's mine plan.

As previously guided, Q2 FY20 production will be impacted by the scheduled 8 week longwall changeout through November and December. New higher capacity long wall chock legs have commenced being received at Narrabri and during this change out these higher capacity cylinders will be installed. The upgrade in support capacity is anticipated to better manage weighting events that occur periodically in the deeper areas of the mine.

3

Gunnedah Open Cut Mines

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

ROM Coal Production

665

801

(17%)

665

801

(17%)

Saleable Coal Production

1,075

1,272

(15%)

1,075

1,272

(15%)

Sales of Produced Coal

1,124

1,407

(20%)

1,124

1,407

(20%)

Coal Stocks at period end

612

909

(33%)

612

909

(33%)

Total ROM and saleable coal production from the Gunnedah open cut mines was down on the prior comparative period due to the closure of the Rocglen mine which saw last ROM coal mined in June 2019, as well as the closure of the Sunnyside mine which saw last ROM coal mined in August 2019, as both these operations transition into rehabilitation phase.

Both saleable production and sales were greater than ROM production as opening ROM stock was drawn down to support strong sales demand.

Tarrawonga Mine

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

ROM Coal Production

429

438

(2%)

429

438

(2%)

Saleable Coal Production

510

521

(2%)

510

521

(2%)

Sales of Produced Coal

575

547

5%

575

547

5%

Coal Stocks at period end

165

471

(65%)

165

471

(65%)

Tarrawonga ROM and saleable production levels were similar to the prior comparative period. High opening coal stocks were drawn down to support sales and attractive blending opportunities.

During the quarter mining equipment arrived on site in preparation for Tarrawonga's expansion to a 3.0Mtpa ROM production mine. It is anticipated the mobile fleet will be largely commissioned during Q4 FY20.

Werris Creek Mine

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

ROM Coal Production

143

167

(14%)

143

167

(14%)

Saleable Coal Production

408

470

(13%)

408

470

(13%)

Sales of Produced Coal

340

541

(37%)

340

541

(37%)

Coal Stocks at period end

346

146

137%

346

146

137%

Werris Creek ROM production for Q1 FY20 was down on the same period in FY19 as the present mining position is not at the same stage of the seam sequence as last year.

For the September quarter, Werris Creek sales were lower than the comparative period.

4

Rocglen Mine

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

ROM Coal Production

-

144

(100%)

-

144

(100%)

Saleable Coal Production

28

195

(86%)

28

195

(86%)

Sales of Produced Coal

77

202

(62%)

77

202

(62%)

Coal Stocks at period end

-

103

(100%)

-

103

(100%)

Last coal was hauled from the mine and processed through the Gunnedah CHPP in July 2019. During the quarter the last coal was sold and the mining operations ceased. Rehabilitation at the mine has commenced.

Sunnyside Mine

Quarter Ended

Year to Date

Thousands of tonnes

Sep 2019

Sep 2018

Change

Sep 2019

Sep 2018

Change

ROM Coal Production

93

52

79%

93

52

79%

Saleable Coal Production

129

85

52%

129

85

52%

Sales of Produced Coal

133

117

14%

133

117

14%

Coal Stocks at period end

101

189

(47%)

101

189

(47%)

Last coal was produced from the mine in August 2019. During the quarter mining operations ceased and rehabilitation of the mine has commenced.

5

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original document
  • Permalink

Disclaimer

Whitehaven Coal Limited published this content on 22 October 2019 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 22 October 2019 00:24:12 UTC