1Q24 RESULTS PRESENTATION

May 03rd, 2024

Tucano Wind Complex

2

1Q24 Highlights

  • Progress in the construction works of Cajuína 2 and AGV VII
  • Significant improvement in wind assets turnaround, with +2 p.p. in availability
  • Increase in the contracting level, capturing price increases
  • Net Margin of BRL 533 million and Adjusted EBITDA¹ of BRL 368 million
  • Effective debt management, optimizing average term and indexation strategies

1 - 1Q24 adjusted for non-recurring events: (i) reversal of Alto Sertão II purchase price; (ii) biennial maintenance of locks; and (iii) indemnification for material damages in Ventos do Araripe.

3

Construction

Operational

Results

Final Remarks

Tucano Wind Complex

Final construction phase of 107 MW, part of over 1 GW built in recent years

4

Cajuína 1 314 MW

100% operational since 4Q23

RN

Cajuína

Cajuína 2 370 MW

Final construction phase of the Castanha Substation, connecting the remaining 13 WTGs

BA

Tucano

52/65

Expected completion in 1H24

Operational

Tucano 322 MW

100% WTGs with COD

40/52

FSA contract stipulates a minimum availability of 98%¹

Substantial

Expected completion in 1H24

Completion

SP

AGV VII 33 MW

AGV VII

Construction on time, on budget

With the commercial operation start of

85%

AGV VII, AES Brasil completes its

Trackers and modules fully assembled

expansion obligations with the state of

São Paulo

construction works completed

Expected completion in 3Q24

1 - 97% during the first year and 98% in subsequent years.

5

Construction

Operational

Results

Final Remarks

Tucano Wind Complex

6

Challenging wind performance in the first quarter

Wind Generation Average Capacity Factor - NE

ONS Data (%) - Generation (MWavg) divided by Installed Capacity (MW)

1Q24 Wind Pattern Anomalies

Data: Consultoria Tempo

Wind Pattern Anomalies at 100 m

(% deviation from the 1991-2020 average)

-15

-11

-7

-2

0

2

7

11

15

37 39

34

28

44

39 40

63

60

52

47 46 45

January

February

March

1Q

2Q

3Q

4Q

2021 2022 2023 2024

Lower average wind speeds result in a decrease

in the energy generated in the country

7

Progress in the turnaround of wind assets during low wind speed periods

Availability

(%, average of the period)

Ventus

Mandacaru & Salinas

Araripe

Caetés

Cassino

87

89

88

95²

97

97

87

89

89

94

83

83

83

85

82

80

52¹

2021

2022

2023

1Q24

2022

2023

1Q24

2022

2023

1Q24

2022

2023

1Q24

2022

2023

1Q24

  • Optimal stock level, enabling efficient equipment replacement
  • Anticipation of preventive maintenance
  • Start of the maintenance internalization process at Ventus

1 - Availability of only 1 out of the 2 transformers in the complex, limiting the maximum availability to ~55%; 2 - In March, the reserve transformer was replaced and energized to begin the repair of the damaged one. Following the energization, Ventos do Araripe's availability remained above 95%.

8

Generation influenced by the low performance of the resource

Availability¹

(%)

+2 p.p.

8789²

1Q231Q24

Generation

(GWh)

965

103

862

Wind

(average speed, m/s)

-10%

7.36.6

1Q23¹1Q24

+10%

1,058

416

643

1Q231Q24

New Assets - Tucano and Cajuína

Wind Portfolio in the Regulated Market

Note: availability and wind data weighted by the installed capacity of the wind complexes; 1 - Excludes Tucano and Cajuína; 2 - Excludes

Salinas Wind Complex

the unavailability of 1 out of 2 transformers at Ventos do Araripe, which limits the maximum availability of the complex to ~55%

9

100% availability in the quarter reflects operational excellence

Availability

(%)

+2 p.p.

98

100

1Q23

1Q24

Generation

(GWh)

+5%

145

153

1Q23

1Q24

Irradiance

(average, W/m²)

+10%

235

259

1Q23

1Q24

Ouroeste Solar Complex

10

ONS reduces hydro dispatch due to disappointing rainy season

Hydrological Scenario

Reservoirs

Inflow

GSF

Average PLD

Load

(%, SIN, average for the period)

(% LTA, SIN)

(%)

(BRL, SE/CO)

(GWavg, average)

80

101

69

78

105

91

61

74

66

66

1Q23

1Q24

1Q23

1Q24

1Q23

1Q24

1Q23

1Q24

1Q23

1Q24

AES Brasil Hydro Plants

Generation

(GWh)

-25%

3,456

2,590

1Q23

1Q24

Availability

(%)

+1 p.p.

91

92

1Q23

1Q24

Barra Bonita HPP

Attachments

  • Original Link
  • Original Document
  • Permalink