1Q24 RESULTS PRESENTATION
May 03rd, 2024
Tucano Wind Complex
2
1Q24 Highlights
- Progress in the construction works of Cajuína 2 and AGV VII
- Significant improvement in wind assets turnaround, with +2 p.p. in availability
- Increase in the contracting level, capturing price increases
- Net Margin of BRL 533 million and Adjusted EBITDA¹ of BRL 368 million
- Effective debt management, optimizing average term and indexation strategies
1 - 1Q24 adjusted for non-recurring events: (i) reversal of Alto Sertão II purchase price; (ii) biennial maintenance of locks; and (iii) indemnification for material damages in Ventos do Araripe.
3
Construction
Operational
Results
Final Remarks
Tucano Wind Complex
Final construction phase of 107 MW, part of over 1 GW built in recent years
4
Cajuína 1 314 MW
100% operational since 4Q23
RN
Cajuína
Cajuína 2 370 MW
Final construction phase of the Castanha Substation, connecting the remaining 13 WTGs
BA
Tucano
52/65 | Expected completion in 1H24 |
Operational |
Tucano 322 MW
100% WTGs with COD | 40/52 | |||
FSA contract stipulates a minimum availability of 98%¹ | Substantial | |||
Expected completion in 1H24 | Completion | |||
SP | AGV VII 33 MW | |||
AGV VII | ||||
Construction on time, on budget | With the commercial operation start of | |||
85% | AGV VII, AES Brasil completes its | |||
Trackers and modules fully assembled | expansion obligations with the state of | |||
São Paulo | ||||
construction works completed | ||||
Expected completion in 3Q24 |
1 - 97% during the first year and 98% in subsequent years.
5
Construction
Operational
Results
Final Remarks
Tucano Wind Complex
6
Challenging wind performance in the first quarter
Wind Generation Average Capacity Factor - NE
ONS Data (%) - Generation (MWavg) divided by Installed Capacity (MW)
1Q24 Wind Pattern Anomalies
Data: Consultoria Tempo
Wind Pattern Anomalies at 100 m
(% deviation from the 1991-2020 average)
-15 | -11 | -7 | -2 | 0 | 2 | 7 | 11 | 15 |
37 39
34
28
44
39 40
63
60
52
47 46 45
January
February
March
1Q | 2Q | 3Q | 4Q |
2021 2022 2023 2024
Lower average wind speeds result in a decrease
in the energy generated in the country
7
Progress in the turnaround of wind assets during low wind speed periods
Availability
(%, average of the period)
Ventus | Mandacaru & Salinas | Araripe | Caetés | Cassino | |||||
87 | 89 | 88 | 95² | 97 | 97 | ||||
87 | 89 | 89 | 94 | ||||||
83 | 83 | 83 | 85 | ||||||
82 | 80 | 52¹ | |||||||
2021 | 2022 | 2023 | 1Q24 | 2022 | 2023 | 1Q24 | 2022 | 2023 | 1Q24 | 2022 | 2023 | 1Q24 | 2022 | 2023 | 1Q24 |
- Optimal stock level, enabling efficient equipment replacement
- Anticipation of preventive maintenance
- Start of the maintenance internalization process at Ventus
1 - Availability of only 1 out of the 2 transformers in the complex, limiting the maximum availability to ~55%; 2 - In March, the reserve transformer was replaced and energized to begin the repair of the damaged one. Following the energization, Ventos do Araripe's availability remained above 95%.
8
Generation influenced by the low performance of the resource
Availability¹
(%)
+2 p.p.
8789²
1Q231Q24
Generation
(GWh)
965
103
862
Wind
(average speed, m/s)
-10%
7.36.6
1Q23¹1Q24
+10%
1,058
416
643
1Q231Q24
New Assets - Tucano and Cajuína | Wind Portfolio in the Regulated Market |
Note: availability and wind data weighted by the installed capacity of the wind complexes; 1 - Excludes Tucano and Cajuína; 2 - Excludes | |
Salinas Wind Complex | the unavailability of 1 out of 2 transformers at Ventos do Araripe, which limits the maximum availability of the complex to ~55% |
9
100% availability in the quarter reflects operational excellence
Availability
(%)
+2 p.p.
98 | 100 |
1Q23 | 1Q24 |
Generation | |
(GWh) | |
+5% | |
145 | 153 |
1Q23 | 1Q24 |
Irradiance
(average, W/m²)
+10% | |
235 | 259 |
1Q23 | 1Q24 |
Ouroeste Solar Complex
10
ONS reduces hydro dispatch due to disappointing rainy season
Hydrological Scenario
Reservoirs | Inflow | GSF | Average PLD | Load | ||||||||||||||||||||||||||
(%, SIN, average for the period) | (% LTA, SIN) | (%) | (BRL, SE/CO) | (GWavg, average) | ||||||||||||||||||||||||||
80 | 101 | 69 | 78 | |||||||||||||||||||||||||||
105 | 91 | |||||||||||||||||||||||||||||
61 | 74 | |||||||||||||||||||||||||||||
66 | ||||||||||||||||||||||||||||||
66 | ||||||||||||||||||||||||||||||
1Q23 | 1Q24 | 1Q23 | 1Q24 | 1Q23 | 1Q24 | 1Q23 | 1Q24 | 1Q23 | 1Q24 |
AES Brasil Hydro Plants
Generation | |
(GWh) | -25% |
3,456 | 2,590 |
1Q23 | 1Q24 |
Availability
(%) | +1 p.p. |
91 | 92 |
1Q23 | 1Q24 |
Barra Bonita HPP
Attachments