4Q22 CONFERENCE CALL

February 28, 2023

2022 Highlights

GROWTH

OPERATIONAL

FINANCIALESG

+456 MW in new

+5% on availability of wind

operational wind capacity

assets in turnaround

Tucano: 95% project

+2% availability of solar

completion

assets

Cajuína 1: 78% project

Integration of new wind

completion

assets to COGE

100% growth in retailer sales

  • +37% in EBITDA¹ reaching
    BRL 1.2 billion
  • +BRL 359 million in Net Income², reaching BRL 320 million
  • Funding for capex 2023
    100% equalized
  • Historical CO2 emissions neutralized
  • 2nd consecutive year rated
    AAA by MSCI
  • 16th consecutive year in the
    ISE B3 portfolio

1 - 2021 EBITDA does not consider the impact of the GSF reimbursement (BRL 35.9 million in 1Q21); 2 - Income adjusted for the impact of the recognition of the tax credit (BRL 532.6 million in 3Q21) and reimbursement of the GSF, net of income tax

AGENDA

Growth

Operational

4Q22 and 2022 Results

Conclusion and Q&A

3

Tucano Wind Complex construction site

Diversified current portfolio, with 65% of Ebitda generated by wind and solar sources

Capacity Installed

2016

Atual¹

6%

+2.5 GW

2.7 GW

5.2 GW

51%

43%

100%

Hydro Wind Solar

In 2022

+456 MW in operational wind assets

Evolution of construction of +1.0 GW wind

  • up to 305 MW of wind pipeline

+BRL 850 million

Additional EBITDA² contracted for the next years

4

1 -Considers 1.0 GW under construction; 2 - Considers estimated annual EBITDA of BRL 600 million in Tucano and Cajuína and BRL 243 million for Ventos do Araripe, Caetés and Cassino

Tucano adds 322 MW of wind energy from the first half of 2023

Civil

Subestation

Transmission Line

Connection Bay

WTGs

99%

100%

2%100%

100%

25%90%

Project

95%

Completed¹

Assembly, Commissioning and Testing Status

48/52

42/52

38/52

24/52

Up to the

Complete

Commissioning

nacelle

Structure

Phase

In operation

5

1 - Based on the physical-financial curve (incurred capex on the total project capex, weighted by the physical progress schedule of the project)