Alt Resources Ltd. provided this update on the planned mining operations at the Tim's Find gold deposit, located in the Mt Ida South region of the Mt Ida and Bottle Creek Gold Project. On the 2nd April 2020 the Company upgraded the Mt Ida and Bottle Creek Gold Project Resource Estimate which includes the Tim's Find project area. The Company has lodged the Tim's Find Mine Plan (TFMP) application with the Department of Mines Industry Regulation and Safety (DMIRS) on 7 April 2020. The application (number 86452) consists of the TFMP with the mine design, haul road access. Tim's Find project currently has a combined JORC 2012 Resource Estimate of 770,600t @ 1.94g/t for 48,400oz Au and a Measured and Indicated Resource Estimate of 535,600t @ 2.11 for 36,375oz Au. In March 2020 the Company executed the Binding Terms Sheet with Blue Cap Mining Pty Ltd. for the Tim's Find Mining Services Agreement (MSA) to undertake mining operations at the Tim's Find project. The Tim's Find haul road (ML29/139) and mine site (M29/421) clearing permits (8763/1) for the project have been approved by DMIRS. Clearing at the mine site and haul road construction can begin prior to mining operations and will commence upon receipt of the Mining Approval from the DMIRS and pending the availability of the Blue Cap mining fleet currently located in Laverton.