Carnegie Wave Energy Limited announced it has completed the onshore power plant for the Perth Project. In addition to completion of the onshore power plant, physical works have now been completed and the plant is ready for connection to the electricity grid at HMAS Stirling pending Western Power approval. Carnegie has received a $54,444 milestone payment from the Western Australian Government under its LEED Grant for the Perth Project.

This payment was awarded for the completion of the onshore plant on Garden Island. Carnegie has also submitted a milestone payment claim worth $316,785 for the completion of this milestone to the Australian Government under its grant from the Australian Renewable Energy Agency (ARENA) Emerging Renewables Program.