For personal use only

NEWS RELEASE

18 January 2022

THICK HIGH-GRADE MINERALISATION IDENTIFIED

AT BARKING GECKO

HIGHLIGHTS

  • Phase 2 follow-up drill program at Barking Gecko North was initiated on 18 November through commencement of diamond drill hole TN270DDT and was successfully completed on 15 December 2021
  • TN270DDT reached a depth of 266m and returned cumulative intersections of 118m at 352ppm eU3O8 from eight intersections between 75m and 265m. Best individual intersections include:
    • 9m at 954ppm eU3O8 from 88m
    • 60m at 304ppm eU3O8 from 150m
    • 30m at 382ppm eU3O8 from 235m
  • The excellent results from TN270DDT will be integrated with previous results from Phase 1 drilling to identify optimal positioning of RC holes planned for the next stage of Phase 2 drilling
  • Next stage of the drill program is scheduled to commence on 24 January and will comprise of 10 RC holes for ~2,500m, with results expected by early/mid-March

Deep Yellow Limited (Deep Yellow or Company) is pleased to announce that the Phase 2 follow-up drill program at the Barking Gecko North prospect (EPL3669) was initiated on 18 November 2021, through the commencement of the program's first diamond drill hole TN270DDT. This hole was successfully completed on 15 December reaching a depth of 266m.

The Barking Gecko prospect is part of the Nova Joint Venture (NJV) located within EPL 3369 in Namibia (Figure 1). Japan Oil, Gas and Metals National Corporation (JOGMEC) completed its 39.5% earn-in obligation through expenditure of A$4.5M in October 2020. Since completion of the earn-in, the NJV parties are now jointly contributing in accordance with their equity holdings as follows:

Reptile Mineral Resources & Exploration (Pty) Ltd - Manager

39.5%

(Subsidiary of Deep Yellow Limited)

Japan Oil, Gas and Metals National Corporation (JOGMEC)

39.5% (Right to equity)

Nova Energy (Africa) Pty Ltd

15%

(Subsidiary of Toro Energy Ltd)

Sixzone Investments (Pty) Ltd

6% (Carried interest)

Namibia

The purpose of drilling diamond hole TN270DDT was to acquire critical core sample material for detailed geological and structural logging to assist with the clarification of the 3D setting of

Page 1 of 14

For personal use only

the highly prospective, strongly mineralised zone discovered at Barking Gecko North (Figure 2).

To date, this zone has only been tested by RC drilling. With completion of hole TN270DDT, the mineralised alaskite intrusions can be more accurately studied to develop a better understanding of the mineralisation controls, enabling optimal positioning of the RC holes planned for the next stage of the Phase 2 drill program.

Figure 1: Location of the Nova JV EPLs 3669 and 3670.

Phase 1 drilling at Barking Gecko North comprised of 14 holes for 3,561m and was completed in October 2021. Importantly, this program returned encouraging results, with 13 of the 14 holes intersecting uranium mineralisation. The standout result was from hole TN258RC, which contained 70m at 503ppm eU3O8 within four intersections over an 83m thick zone from 178m depth, as reported on 5 August and 19 October 2021.

Page 2 of 14

For personal use only

Phase 1 NW-SE orientated drilling in the central area delivered the best results. TN270DDT was targeted to undercut this mineralisation and intersect an east-west-trending fault, interpreted from magnetic data, which is considered to influence the setting of the mineralisation.

TN270DDT was angled 70 degrees to the north to obtain orientated core to better define, understand and confirm the structural setting of this mineralisation, which to date, was interpreted from RC drill chips and down-hole optical televiewer (OPTV) surveys.

TN270DDT intersected 118m at 352ppm eU3O8 from 75m using a 100ppm eU3O8 cut-off grade occurring within eight intersections over a 190m interval. This confirms the strong mineralisation associated with this prospect, the northeast-southwest trend of the mineralised intrusions and the presence of an east-west trending fault. The best continuous intersections within the mineralised envelope include 10m at 954ppm eU3O8 from 88m, 60m at 304ppm eU3O8 from 150m and 30m at 382ppm eU3O8 from 235m.

Early inspection of the core indicates a general SW-NE dipping trend of the mineralised intrusions. More detailed work is currently in progress to confirm this trend and to identify the nature of the specific mineralised intrusions and their 3D settings within the general mineralised envelope.

Drill hole location including drill hole trace and intersections are shown in Figure 2.

Figure 3 shows a northwest-southeastcross-section projecting TN270DDT onto that section.

The drilling results continue to confirm the exceptional thickness and grade of previous drilling. The next stage of Phase 2 RC drilling is planned to start 24 January, to further evaluate the possible economic significance of Barking Gecko North.

In-house portable XRF (pXRF) assaying of all mineralisation at Barking Gecko North is in progress. Preliminary results confirm that mineralisation is uranium dominant, with minor thorium associated.

The mineralised eU3O8 intersections of TN270DDT are listed in Table 1 of Appendix 1.

Drill hole details of TN270DDT are shown in Table 2, Appendix 1.

Page 3 of 14

For personal use only

Figure 2: EPL3669, Barking Gecko North drill hole locations showing

GT colour coded drill hole collars over basement geology.

Figure 3: EPL3669, Barking Gecko North, NW-SE drill section.

Page 4 of 14

For personal use only

CONCLUSION

The results from TN270DDT, in conjunction with Phase 1 drilling at Barking Gecko North, remain encouraging, with the prospective nature of this zone being confirmed.

The size of the prospective zone containing high grade and thick uranium mineralisation, as identified to date, appears to be restricted at this stage to 700m by 200m. However, further drilling is required to test the continuation of the mineralisation to the north and south as well as at depth.

The interesting feature of Barking Gecko North is the high-grade character of the mineralisation that is being encountered, which is very similar to what is found at the near-adjacent Rossing and Husab uranium deposits. On this basis alone the follow up drilling that is planned on this target is highly justified

The next stage of Phase 2 drilling will comprise of 10 RC holes for 2,500m and is planned to start 24 January. Results are expected by early/mid-March.

Yours faithfully

JOHN BORSHOFF

Managing Director/CEO

Deep Yellow Limited

This ASX announcement was authorised for release by Mr John Borshoff, Managing Director/CEO, for and on behalf of the Board of Deep Yellow Limited.

For further information contact:

John Borshoff

Managing Director/CEO

  1. +61 8 9286 6999
  1. john.borshoff@deepyellow.com.au

Page 5 of 14

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Deep Yellow Limited published this content on 17 January 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 17 January 2022 20:54:03 UTC.