Dilip Buildcon Limited announced that the Project of CONSTRUCTION OF BRIDGE INCLUDING APPROACHES ACROSS RIVER ZUARI ON NH-17/NH-66 ON PANJIM-MANGALORE SECTION IN THE STATE OF GOA-(PACKAGE II: CH 530/850 TO CH 531/934) (NH-12014/04/2015 GOA (P-6)) through an Engineering, Procurement and Construction (EPC) Contract" has been completed. The Completion Certificate has been issued by the authority and has declared the project fit for entry into operation as on September 30, 2023. Mode: EPC.

Project Cost: INR 5,454 million. Appointed date and Construction period: April 11, 2016 (1096th day from Appointed Date (36 months)). Scheduled Completion date: April 12, 2019.

Revised Scheduled Completion date including EOT: August 31, 2023. Completion date: September 30, 2023.