Dilip Buildcon Limited announced that the Company has declared as L-1 bidder for the tender floating by the Haryana Rail Infrastructure Development Corporation Limited on EPC mode in the state of Haryana. Details of the project are as under: Project, Bid Project Cost Including GST (Rs. in Cr.), Mode, Completion period, Length, "HRIDC - EPC -Prithla to Dhulawat Contract Package C5: Composite Contract package in connection with New BG Double Railway Line of HORC project between stations Prithla and Dhulawat for: (i) Design and Construction of Civil Works (Earthwork, Bridges, Stations and Retaining Walls) from km -2.296 to km 12.00 & km 18.00 to km 20.942; (ii) Design & Construction of viaduct from km 20.942 to km 24.844; (iii) Design & Construction of Ballastless track from km 20.842 to km 24.8 44; and, (iv) Design, Supply, Installation, Testing & Commissioning of General Electrical Services from km-2.296 to km12.00 and Km 18.00 to Km 24.844.

Bid Project Cost Including GST is INR 10,924.6 million. Mode is EPC. Completion period is 36 Months.

Length is 21.14 Km.