KSB Limited is in the process of constructing a new shed in the available space at its Sinnar plant at Nasik, Maharashtra. The proposed construction of shed is to optimise the use of the available space at the said plant. At present, the use of proposed shed is intended for raw material storage, small sub-assemblies, Manufacturing of Global pumps series and Solar products along with the activities like painting, testing and packing.

existing capacity at Sinnar: plant; 1,95,000 Pumps per year existing capacity utilization at Sinnar plant; 93%. proposed capacity addition; @ 30% increase in the capacity of Global pump manufacturing is expected due to this expansion. period within which the proposed capacity is to be added; The construction of the shed is expected to be completed by March 2024 investment required; INR 320 Million tentatively.

mode of financing; Only internal accruals. rationale Optimisation of the available space at the plant to cater to future growth.