Mexus Gold US announced that it has completed phase 1 of its new heap leach pad. The 250,000 ton pad, which is expandable to 1,000,000 tons, will have crushed mineralized material placed beginning 11/17. This material, averaging 2.7 Gpt Au, should begin leaching by 11/21. The company is looking for a return of .6 Gpt Au in solution. Start up flow at 10.5 liters per second is expected to return approximately 17.5 oz Au per 24 hour cycle. Mexus is targeting 12/1 to meet this goal.