Origin Materials, Inc. continues to expect the construction of Origin 1 manufacturing plant to be completed before the end of 2022, with commissioning and production at the plant beginning immediately thereafter. As of June 30, 2021, installation of most foundations for building and process areas was significantly underway and on track for timely Origin 1 mechanical completion. In addition, Origin has also completed fabrication of the modules that contain all the equipment used for the conversion of biomass feedstock into high value chemicals. By the end of 2021, Origin expects the modules to be lifted and erected, roughly four months ahead of original schedule. Origin continues to expect the construction of Origin 2 manufacturing plant will be complete by the middle of 2025.