The well produced first oil at approximately 0930 US Central Time on
The operator had planned a well production ramp up strategy where production would slowly be increased in 1,000 bopd increments until the well reached a steady state production rate. The plan involved the slow ramp to ensure the effective 'cleanup' of completion fluids and the 10-mile subsea pipeline.
The well intersects the following independent high-quality oil-bearing reservoir intervals: DTR-10 where a net 140 feet of TVD oil pay was encountered and MP where a net 110 feet of TVD oil pay was encountered. This reservoir is expected to perform consistent with analogue wells in the GC 18 field.
Due to multiple weather delays, upon completion, the well was left shut in for 24 days before initial flowback commenced. As reported, the well was then flowed for approximately 7 days before an additional hurricane caused both the well and its associated production platform to be shut in. Upon return from this event, it was discovered that a section of the primary oil export flowline was impacted by the hurricane and required minor repairs before production could recommence on
Since returning to production on
A comprehensive review is ongoing of the conditions surrounding the drilling of the MP sands, the setting of the production casing, perforating, and the completion and stimulation activities. Additionally, the review of the well performance data, including a bottomhole pressure build up test that was conducted while the well was shut in from 22 October to 7 November due to the hurricane and subsequent pipeline repair period, is being evaluated. The well will continue to flow at the current rate while additional engineering analysis is completed to determine whether a well intervention and stimulation could enhance the current well deliverability, or if a recompletion is warranted.
Consistent with its continuous disclosure requirements, Otto will continue to update the market on the performance of the GC 21 'Bulleit' field.
The project has been developed via a 10-mile subsea tieback to the GC 18 Whistler platform where production is being processed and then delivered into regional oil and gas sales pipelines. Otto's product sales from GC 21 are secured via long term production handling, transportation and sales arrangements.