Roach told Proactive's Stephen Gunnion the company has made progress in addressing some design issues within the project, enhancing the efficiency of material processing for the floatation plant. Roach detailed upcoming modifications to the plant's plumbing, expected to resolve remaining challenges, particularly in the flotation section, aimed at improving recovery rates. These modifications are part of the project's final stages before commissioning.
In addition to operational updates,
Investors are advised to look for upcoming milestones, particularly improvements in the flotation process expected to enhance production tonnages. The company remains focused on resolving the final challenges of the flotation plant to reach its production goals.