Prismo Metals Inc. provided an update for its ongoing drill program at the Palos Verdes property located in the Panuco district in Mexico. The Company has drilled 2,620 meters in the current program and completed thirteen holes with one hole in progress, PV-23-32. One additional hole is contemplated after completing hole PV-23-32 as part of the original drill program which began in May.

This will be followed by the previously announced expansion of the drill program, with holes to be drilled from Vizsla Silver Corp. concessions adjacent to the Palos Verdes concession. These holes will target the Palos Verdes vein at depth.

This follows a recommendation presented by the Panuco Joint Technical Committee to drill approximately 3,600 meters in ten holes to be completed in two phases.