Prospect Resources Limited (ASX: PSC, FRA: 5E8) (Prospect or the Company) is pleased to announce the results of the Staged Optimised Feasibility Study (Staged OFS) on its 87%-owned Arcadia Lithium Project (Arcadia or the Project).

The Staged OFS reflects the strong potential of Arcadia to become a compelling long life, large scale, hard rock open pit lithium mine in Zimbabwe, Southern Africa. It confirms that the Project is among the best in the world for scale and cost of production when compared to existing operations and other prospective projects. A key competitive advantage lies in the quality of the lithium concentrate products, being high in grade and very low in impurities.

Arcadia is a relatively simple and robust development, with high grades and low strip ratios enhancing financial outcomes. The Project delivers outstanding returns independent of by-product credits and the lithium price environment. The staged development pathway outlined in this Staged OFS presents a lower upfront capital hurdle, with an approach that addresses all technical, commercial and operating risks, and delivers a progressive ramp up and ability to further optimise Stage 2 (delivering 2.4 Mtpa throughput).

This study has been prepared by leading engineering consulting business, Lycopodium, with assistance from Prospect and selected external contributors. Where required Lycopodium provided direction in the planning and execution of programmes designed to reduce technical risk, resulting in increased confidence and accuracy in process development, engineering design and cost estimation. Forecast project economics are expected to be substantially improved via the direct 2.

4Mtpa development pathway, which is currently the subject of a detailed study (the Direct OFS) scheduled for completion in Q4 2021. Current engagement with a range of strategic groups under a formal partnership process (being managed by Azure Capital and Vermillion Partners) is focused on the development and financing of Arcadia under the Direct OFS.

HIGHLIGHTS

Staged Optimised Feasibility Study (Staged OFS) confirms strong technical and economic viability of Arcadia under a staged development pathway

Staged OFS completed by external study manager and leading engineering consulting firm, Lycopodium, to +/-12.5% capital expenditure estimate accuracy, building on the technical assessments undertaken in the 2019 DFS

Progressive construction of two 1.2 Mtpa modules delivers lower upfront capital costs, with reduced execution and market risk

Ore Reserve increase from 37.4Mt to 42.3Mt, reflecting increased pricing offset by lower metallurgical recoveries

De-risked Project execution, process flowsheet and market integration with construction and operation of Arcadia Pilot Plant and qualification samples sent to customers

Project economics expected to be further improved in Direct-to-2.4 Mtpa Optimised

Feasibility Study (Direct OFS), due for completion in Q4 2021

Partnership process being managed by Azure Capital and Vermilion Partners remains on-track, with strong interest from several groups focused on the Direct OFS outcomes

Prospect Managing Director, Sam Hosack, commented: 'It is very pleasing to have a viable alternate to the direct development pathway, being a progressive modular build to 2.4 Mtpa, now validated by the Staged OFS undertaken by Lycopodium. This study confirms Arcadia as one of the only independent, shovel-ready projects globally without offtake totally locked up. It highlights that Arcadia is one of the world's premier hard rock lithium assets, with outstanding projected returns under a more conservative development pathway.'

'The OFS details our clear differentiation with a range of potential product markets, and customers versus traditional spodumene projects. Even at the smaller initial scale, the Lycopodium results demonstrate a highly competitive forecast operating costs and margins, reflecting prices for technical petalite at a significant premium to traditional chemical grade spodumene concentrate pricing.' 'With strong lithium market conditions, and with renewed interest from potential partners, we are now completing the work on the Direct OFS pathway case before funding decisions are made

Brief Overview

Arcadia is located in the Mashonaland East District of Zimbabwe, approximately 38km east of the Capital, Harare (1746'26' S 3124'34' E). It is positioned within an established mining jurisdiction, where mining and export of lithium products has been ongoing for over 60 years. Arcadia is owned by Prospect, through its 87% owned subsidiary, Prospect Lithium Zimbabwe (pvt) ltd (PLZ). The Project occupies an area of more than 9km2 and incorporates historical lithium and beryl workings, and the existing Pilot Plant producing technical grade petalite samples.

The Project is close to major highways and railheads. The nature and location of the Port of Beira (a regional export hub located less than 600km from Arcadia by road transport) is also a key advantage. Arcadia's proximity to Harare provides access to a source of skilled and semi-skilled labour, and qualified technical and commercial personnel. Arcadia is situated in close proximity to key infrastructure, including being 11km from the major power transmission line between the region's largest hydro-electric facilities, providing ease of interconnection, and reliability of supply

In November 2018, Prospect released a Definitive Feasibility Study (DFS) on the Project. Subsequent work on the Mineral Resource, mine design, metallurgical testing programmes and product marketing resulted in an Updated DFS completed in late 2019.

The Updated DFS embedded a market-driven approach in which the production and sale of premium ultra-low iron, technical grade petalite concentrate was a key driver of development strategy. This strategy fed into mine planning and in turn influenced the design of the primary petalite recovery circuit such that production of technical grade petalite was maximised.

The Arcadia Staged OFS

The capital estimate of the Staged OFS has been prepared in accordance with the Lycopodium Cost Estimating Procedures and fulfils the requirement of the AACE Class 2 Estimate ('Bankable Feasibility Estimate') with an accuracy range of +/- 12 %. The study manager is Lycopodium (process plant design and review, plant capital and operating cost estimates), with key external study consultants including CSA Global (ore reserve, mine planning), Practara Ltd (geotechnical services), SRK Consulting (environmental assessment) and Roskill Consulting (price forecasting). The Staged OFS has confirmed the strong technical and economic viability of conventional open pit mining and gravity processing of the world-class Arcadia project via a staged development to 1.2Mtpa (Stage 1), and then 2.4Mtpa (Stage 2) throughput.

Key Arcadia physical outcomes

A Measured, Indicated and Inferred Mineral Resource estimate for Arcadia of 72.7 million tonnes at 1.11% Li2O was published in an ASX release dated 25 October 2017. The resource model was updated to include drilling conducted since 2017. There was no change to the overall tonnage but resulted in a change to the grade, due to the increased accuracy of the modelling of the orebody. Both the 2017 declaration of resources and the 2021 declaration have reported in accordance with the JORC Code

The life-of-mine (LOM) strip ratio is approximately 3.4 (waste tonne to ore tonne). The Ore Reserve is the economically mineable part of the Measured and Indicated Resource. It includes mining dilution of 5% and allowance for losses in mining of 5%. Appropriate assessments and studies have been carried out and include consideration of modification by realistically assumed mining, metallurgical, economic, marketing, legal, environmental, social and government factors.

Mining

The Arcadia deposit is to be mined as a conventional truck and shovel open pit operation via contract mining. Waste dumps will be located as close as possible to pit exit points to minimise haulage profiles without disrupting the access to the minable resource or crushing plant. The mining schedule developed is to suit the strategy of commencing ore treatment operations at 1.2 Mtpa and subsequently upgrading to 2.4 Mtpa after 4 years of operation. Maximum annual mining rates are just under 14Mtpa of total material (waste plus ore).

Processing

The key focus of processing strategy in the Staged OFS (and Direct OFS) process has been the further reduction of risk and the increase of certainty for Arcadia processing. The Staged OFS is based on a global lithia recovery of 51.3%, comprising assumed (spodumene recovery of 78.2% and assumed petalite recovery of 31.3%), with assumed tantalum recovery of 27.0%.

These assumptions are based on the extensive testwork undertaken to date, as well as the learnings from the pilot plant operation. Since publishing the 2019 Updated DFS, additional variability testing has been done on the 2 main ore bodies (Main Pegmatite and Lower Main Pegmatite), which constitute > 79% of the Ore body. This extensive testwork included flotation configuration changes and optimum flotation parameters under locked cycle conditions.

Locked cycle testwork is a standard process requirement to assess the consequential effects of process recycle streams on the circuit mass balance and recoveries while also serving as a conventional way to mitigate flotation circuit design risk. The study has yielded lower LOM spodumene recoveries of 78.2% compared to the previous assumption of 84.5%, utilised in the 2019 DFS. These spodumene recoveries are now more in line with peers in the global lithium industry. Opportunities do exist for further recovery optimisation before entering the detailed Engineering design phase.

Forecast average LOM production is 133kt per annum of spodumene concentrate, 86kt per annum of technical grade petalite concentrate and 21kt per annum of chemical grade petalite concentrate, with a peak of 338 kt per annum total volume.

An initial ramp-up of six months has been incorporated for the processing plant to obtain Stage 1 nameplate capacity of 1.2Mtpa and assumed recovery levels. Conventional beneficiation techniques including dense medium separation (DMS) to recover petalite, gravity-based processes to recover tantalite, and froth flotation to recover spodumene have been retained.

Key areas of later testing included the use of high pressure grinding rolls (HPGR) technology, ongoing DMS optimisation and locked cycle spodumene flotation. Testwork was carried out on Main Pegmatite (MP) and Lower Main Pegmatite (LMP) ore zones during 2019 and 2020, and the data derived from these programmes has been applied by Lycopodium to current process and engineering design. Optimisation of tantalum recovery was continuing at the time of study preparation.

Two-stage crushing followed by HPGR has been selected to achieve the sub 5 mm crush size required to achieve adequate liberation of petalite for primary recovery by DMS. DMS feed preparation is based on secondary crusher product feeding HPGR crushing operating at medium pressure. Approximately 68% of plant feed will report to DMS at a bottom cut-off size (BCOS) of 0.6 mm. Primary crushing capacity will be set at 2.4 Mtpa from the outset.

The target grade for petalite products is 4% Li2O, i.e. 82% petalite. DMS testwork has demonstrated that 80% of all DMS petalite concentrates produced from Arcadia ores coarser than 1.7 mm will meet specifications for technical grade product, with Fe2O3 substantially less than 0.05%. The remaining 20% finer petalite at -1.7 mm +0.6 mm will be suitable as chemical grade product. Recoveries of petalite to Technical Grade and Chemical Grade products are expected to be 25% and 6% of plant feed petalite respectively.

The sub-millimetre spodumene grain size limits recovery of spodumene by DMS. Consequently, all ore post gravity recovery will report to the flotation circuit where spodumene is effectively recovered at a grind size P100 of 0.212 mm (P80 0.150 mm). Fatty acid flotation of spodumene is widely practised in the lithium beneficiation industry and Arcadia will be no exception in this regard. The target grade for spodumene concentrate is 6% Li2O; i.e. 75% spodumene. Based on flotation data accumulated to date, expected spodumene recovery to concentrate is about 81% for LMP ore and about 55% for MP ore. The iron content of spodumene concentrate is expected to be about 0.3% to 0.5% Fe2O3. Spodumene concentrate will be cleaned, and upgraded, by employing mica flotation at low pH followed by WHIMS to reduce iron contamination. The mica concentrate will be set aside pending potential identification of a potential commercial opportunity to realise value from this product.

Contact:

Sam Hosack

Email: shosack@prospectresources.com.au

About Prospect Resources Limited (ASX: PSC, FRA:5E8)

Prospect Resources Limited (ASX: PSC, FRA:5E8) is an ASX listed lithium company based in Perth with operations in Zimbabwe. Prospect's flagship project is the Arcadia Lithium Project located on the outskirts of Harare in Zimbabwe. The Arcadia Lithium Project represents a globally significant hard rock lithium resource and is being rapidly developed by Prospect's experienced team, focusing on near term production of high purity petalite and spodumene concentrates. Arcadia is one of the most advanced lithium projects globally, with a Definitive Feasibility Study, Offtake Partners secured and a clear pathway to production.

About Lithium

Lithium is a soft silvery-white metal which is highly reactive and does not occur in nature in its elemental form. In nature it occurs as compounds within hard rock deposits (such as Arcadia) and salt brines. Lithium and its chemical compounds have a wide range of industrial applications resulting in numerous chemical and technical uses. Lithium has the highest electrochemical potential of all metals, a key property in its role in lithium-ion batteries

Caution Regarding Forward-Looking Information

This announcement may contain some references to forecasts, estimates, assumptions and other forward-looking statements. Although the Company believes that its expectations, estimates and forecast outcomes are based on reasonable assumptions, it can give no assurance that they will be achieved. They may be affected by a variety of variables and changes in underlying assumptions that are subject to risk factors associated with the nature of the business, which could cause actual results to differ materially from those expressed herein. All references to dollars ($) and cents in this announcement are in United States currency, unless otherwise stated.

Investors should make and rely upon their own enquiries before deciding to acquire or deal in the Company's securities. Prospect confirms that for the purposes of Listing Rule 5.19.2, all material assumptions underpinning the information continue to apply and have not materially changed

(C) 2021 Electronic News Publishing, source ENP Newswire