Back in 2013, the Technology and Construction Court (TCC) decision in
Fast forward some eight years and we have the first reported case to cite the Parkwood decision. We review the judgment in
Background
- In 2015, Simply were engaged by a third party to design and construct a care home in Mill Hill that was in due course occupied and operated by Abbey The contract was an amended form of JCT Design and Build Contract 2011 with
June 2015 updates (theBuilding Contract ). -
Practical completion was certified in
October 2016 . -
In 2017, by a novation agreement, the third party transferred all its rights and obligations under the building contract to
Toppan , the owner of the care home. -
In mid-2018, fire safety defects were discovered in the care home. In
January 2019 , Simply was notified of these defects, which were subsequently rectified by another company. -
In 2020, the parties executed the collateral warranty whereby Simply warranted to Abbey that it had performed and would continue to perform its obligations under the
Building Contract (the Abbey Collateral Warranty). -
Adjudications followed, including a claim by Abbey against Simply under the Abbey Collateral Warranty for loss of trading profits, and a claim by
Toppan against Simply under theBuilding Contract arising out of the remedial works. Abbey andToppan succeeded in the adjudications and were awarded approximately Ł908,000 and Ł1 million respectively by the (same) adjudicator - Simply did not pay. - These TCC proceedings were commenced in order to enforce the two adjudication decisions against Simply.
Various matters were in issue in the proceedings. We concentrate here on the arguments between Abbey and Simply relating to the Abbey Collateral Warranty and whether or not it comprises a "construction contract" under the Construction Act. If the Abbey Collateral Warranty is not a construction contract, then the adjudicator did not have jurisdiction to decide this dispute and the award will not be enforceable.
The Construction Act
Section 104(1) of the Construction Act provides:
"In this Part a "construction contract" means an agreement with a person for any of the following -
- the carrying out of construction operations;
- arranging for the carrying out of construction operations by others, whether under sub contract to him or otherwise;
- providing his own labour, or the labour of others, for the carrying out of construction operations
(2) References in this Part to a construction contract include an agreement -
- to do architectural, design, or surveying work; or
-
provide advice on building, engineering, interior or exterior decoration or on the laying-out of landscape,
in relation to construction operations..."
The Judge in
- a construction contract does not have to be wholly or even partly prospective - being retrospective in effect is not in itself a bar to it being a construction contract under the Construction Act;
-
s104 of the Construction defines a construction contract as "an agreement "for... the carrying out of construction operations" -
Parliament intended this as a "wide definition"; - where one party to a contract agrees to carry out and complete construction operations, it will usually be an agreement "for the carrying out of construction operations" under the Construction Act.
The Parkwood Collateral Warranty was held to be a construction contract under the Construction Act. Mr
Mr
The Abbey Collateral Warranty
The key substantive terms of the Abbey Collateral Warranty provided (in summary) that Simply warranted that:
- it has performed and will continue to perform diligently its obligations under the
Building Contract ; and - in carrying out and completing the works and design, Simply has exercised and will continue to exercise all reasonable skill care and diligence.
The TCC held that the Abbey Collateral Warranty was not a "construction contract" under the Construction Act as it was not an agreement for "the carrying out of construction operations".
Key considerations included that:
- the Abbey Collateral Warranty was not executed until four years after practical completion and 8 months after remedial works had been completed by another contractor; and
- the Abbey Collateral Warranty gave a warranty in favour of the beneficiary but did not refer to any "acknowledgment" or "undertaking" in its favour (in contrast to the Parkwood Collateral Warranty).
As the Abbey Collateral Warranty was not a construction contract under the Construction Act, there was no contractual right to adjudicate, and the adjudicator's decision could not be enforced.
Commentary
The decision in
The right to adjudicate is valuable to the beneficiary of a warranty but it seems likely that the construction industry will continue to accept that collateral warranties are now drafted to ensure (as far as possible) that the Construction Act will not apply.
Read the original article on GowlingWLG.com
The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.