Touchstone Exploration Inc. announced that the Coho facility has safely delivered first natural gas, representing the first onshore natural gas project to come onstream in Trinidad and Tobago in over twenty years. The Coho area is located in the Ortoire block, where Touchstone has an 80 percent operating working interest and Heritage Petroleum Company Limited holds the remaining 20 percent working interest. On September 26, 2022, the Coho facility was approved by the Certified Verification Agent with the Trinidad and Tobago Ministry of Energy and Energy Industries promptly authorizing facility commissioning.

On September 27, 2022, the company commenced commissioning and achieved commercial deliveries on October 10, 2022, with a field estimated sustained gross production rate of approximately 10.5 million cubic feet per day (approximately 8.4 million cubic feet per day net). The company will continue to monitor the Coho-1 well in an effort to optimize production. In conjunction with initial production, the company have sold the 2.7-kilometre, 6-inch gathering line tying in Coho facility to the Baraka natural gas facility to The National Gas Company of Trinidad and Tobago Limited.

Natural gas production from the Coho facility will be sold to NGC pursuant to a natural gas sales agreement executed in December 2020.