The improved operating performance in the first quarter has been considerably overshadowed by the COVID-19 crisis. Faced with a significant humanitarian challenge, the Company's first priority has been to take all the necessary actions to safeguard the wellbeing of our people and to provide support to the extent required in the communities in which we operate.

Where possible, employees are working remotely from home. At all global manufacturing operations we are following government and World Health Organisation advice and guidelines in order to protect employees and prevent the spread of infection.

Before the Company started to address the business disruption we are facing, we first had to ensure that our manufacturing facilities were safe places to work. We have therefore introduced practical changes to our facilities which fall into three distinct, but equally important areas: enhanced cleaning and hygiene, social distancing and personal protective equipment (PPE).

With the dedicated support of our employees and stakeholders, the Company has been able to adapt decisively to protect the business in the face of this completely unprecedented scenario and meet remaining customer demand from a reduced level of production.

2

2

The Company performance improved in the 1Q'20, with EBITDA increasing by 4.5% to $1.0bn vs 4Q'19. This improvement reflects the positive momentum in our markets at the beginning of the year, following the end of destock activity that had negatively impacted our core markets in the latter part of 2019.

This positive momentum, however, came to an abrupt halt from mid-March, as the global escalation of the COVID-19 pandemic, and subsequent measures introduced by governments worldwide to contain it, negatively impacted economic activity and industrial supply chains in many parts of the world. We see strong parallels with the impact faced during the global financial crisis in 2008/2009 and draw on our experience of successfully navigating this period. As discussed on the previous slide, our first and most important priority is to ensure the health and wellbeing of our people in this challenging environment.

The Company has rapidly adapted production in-line with the demand environment. We continue to remain agile in terms of adapting production to demand and ensuring that our assets are maintained appropriately to enable them to restart when the situation improves.

In order to mitigate in part, the effect of weaker demand, the Company has temporarily reduced fixed costs in line with lower production as well as implement other cost saving measures. We have seen governments worldwide announce unprecedented measures to provide support for which we are thankful. We have made use of such schemes before but never in such a comprehensive way.

The Company has also cut its spending and the cash needs of the business have been reduced by $1bn. The largest part of this is the reduction of capex plans for FY'20 to $2.4bn. All non-essential capex has been suspended, while certain high return projects like the Mexico hot strip mill project, agreed Italian projects and certain projects to reduce CO2 emissions will continue. And the overall maintenance capex expense is expected to be lower due to reduced operating rates.

The Company has entered this unprecedented period with a far stronger balance sheet than previous crisis environments, reflecting its deleveraging priority in recent periods. Due to effective cash management in 1Q'20, net debt remained near the historical low levels at the end of 2019. Further, we have supplemented our already strong $9.8bn liquidity position at March 31, 2020 with a new $3bn credit facility.

The $7bn net debt target remains a key priority. And despite the COVID-19 pandemic challenges, the Company's $2bn asset portfolio optimisation program is progressing on track.

Against the backdrop of significant cost savings measures being taken across the business, the Board determined it both appropriate and prudent to suspend dividend payments until such a time as the operating environment normalizes. As a result, no dividend from 2019 results will be proposed to shareholders at the Annual General Meeting now scheduled in June 2020.

3

3

On this slide we highlight the responses and contributions ArcelorMittal has contributed in the collective effort to fighting the COVID-19 pandemic across the globe, not only in our workplace but through our support for public health efforts and community support programmes.

First and foremost, where our operations continue, we have made extensive efforts to adapt our safety philosophy to cover all the aspects of hygiene, personal protection, social distancing and shared vigilance needed to protect our workforce.

Secondly, we have made tremendous efforts to support the public response to care for people struck by the virus, with donations of vast amounts of medical and protective equipment to local hospitals, to nursing homes and community organisations across Europe, Africa, and the Americas.

We engage with local communities to understand their needs and concerns. For example, in Brazil, we have made a donation to enable the Joao Monlevade hospital to double its number of intensive care beds. In Liberia, made cash donations to the Ministry of Health to purchase medical equipment, and we are working with a local NGO to tackle social stigmas associated with COVID-19. Across West Africa we are coordinating efforts to mobilise the resources of the private sector to support efforts against the coronavirus, as we did during the Ebola crisis. In India, we are supporting the Prime Minister's CARES fund and donated food kits for over 30,000 people. And in many countries, we are also supporting thousands of children who are being schooled at home, developing online videos and educational tools in Ukraine, and donating 5000 laptops in Spain.

Thirdly, the Company has leveraged its global R&D capabilities in adapting its 3D printing expertise to design ventilators with the Spanish authorities. These designs will be shared so that 3D printing networks across the world can use them. As well as 3D printing ventilators for Spanish hospitals, we are also producing 3D printed face shields in Spain, Mexico and Brazil, both for use by health workers and by those working in essential industries such as steel.

All these contributions have been designed by ArcelorMittal people who are taking the time to listen, and to respond with care, often going far outside their normal responsibilities. For all this the Company is truly grateful and proud.

4

Pausing for a moment to reflect on the sustainable development progress during 1Q'20. ArcelorMittal's ambition is to invent smarter steels for a better world, and vital to this is the pursuit of sustainable development. In 2015, we launched ten sustainable development outcomes for our business, which describe the business we need to become, if we are to bring optimal long-term value to our people, our stakeholders and the environment. The Company highlights the progress of two particular programmes during 1Q'20 that demonstrate its commitment to becoming that business. Firstly, ArcelorMittal began in the first quarter of 2020 its program to certify all our Europe Flat sites against the first ever ResponsibleSteel standard by the end of 2020. The standard covers 12 environmental, social and governance principles including climate, water stewardship and human rights, and we believe certification will reassure our customers of the high sustainability standards we uphold at our sites. The timing of this certification program may be somewhat delayed as we adapt our work program in response to COVID-19 but nonetheless, we hope to receive our first site certifications this year.

Secondly, our commitment to the Paris climate agreement remains unwavering, with our ambition to significantly reduce our carbon footprint and become carbon neutral in Europe by 2050. Our Europe Flat segment is working towards its medium-term target of reducing Scope 1 carbon emissions by 30% by 2030 over 2018, and the Company plans to publish its roadmap to achieving this target shortly. ArcelorMittal's transition strategy is based on both a broad and flexible low-emissions innovation program - which led CDP to award us top place in their ranking of transition opportunities - and our work to develop effective forms of policy support. We outlined our thinking on this in our first Climate Action Report last year, and we were pleased to see that our governance, strategy and progress on climate gained us an 'A-' score in the 2019 CDP Climate Survey in January this year.

Work on our low emissions innovation program continues. Key to our ability to roll these technologies out in our steel plants will be the introduction of appropriate policy support measures that ensure, in effect, that low-emissions steel becomes more competitive than high-emissions steel. One such

5

measure is a form of carbon border equalization: We believe this to be an important mechanism which could even motivate other regions in the world to implement a carbon price, avoid circumnavigation, create a fair market and, crucially, encourage investment in lower-emissions steel production. Another key aspect of policy will be measures that accelerate the sustainable financing both of these new technologies and the energy infrastructure to support them.

5

Turning to the financial performance, ArcelorMittal reported EBITDA of $1.0bn for 1Q'20. This is an improvement from 4Q'19 performance (+4.5%). Despite the negative impacts of COVID-19 from March onwards, our 1Q'20 steel performance improved by 7.3% QoQ, with improvement in NAFTA, Europe and ACIS offset by seasonally weaker Brazil. Mining segment EBITDA was stable in 1Q'20, with the effect of lower seaborne iron ore shipments (-11% QoQ, in part due to COVID 19 impact but also unplanned maintenance and seasonality in AMMC) being offset largely by the benefit of lower freight costs.

We reported net loss of $1.1bn in 1Q'20. Adjusting for the impact of impairment charges (impairment of Florange coke battery following its closure to reduce costs) and exceptional items (including inventory related charges in NAFTA and Europe due to weaker pricing outlook due to COVID-19) the adjusted net loss would have been $0.6bn. In terms of cashflow performance, the Group has performed well. We had a small investment of $0.1bn in working capital during 1Q'20. This follows the normal seasonal pattern of the business, but given the Company's focus on working capital management, the investment this quarter is less pronounced than in prior years.

Net debt increased marginally to $9.5bn as of March 31, 2020 as compared to $9.3bn as of December 31, 2019. This is $1.7bn lower as compared to March 31, 2019.

As of March 31, 2020, the Company had liquidity of $9.8bn, consisting of cash and cash equivalents of $4.3bn and $5.5bn of available credit lines which was strengthened further in early May by a new $3bn credit facility.

6

As highlighted on slide 3, the Company has acted swiftly and rapidly to adapt production in-line with the reduced demand environment caused by COVID-19.

Production has been impacted across all segments and regions, with the main impacts detailed on the slide. Given these impacts the Company expects steel shipments in 2Q'20 to be within the range of 13.5Mt to 14.5Mt.

The Company remains agile and flexible in adapting production to changes in demand. Robust plans and maintenance practices will ensure that our assets are able to increase production quickly as and when demand improves.

7

During this exceptional demand situation, an essential action is to reduce costs as quickly as possible, to a level consistent with the reduced output. The concept of "variablising" fixed costs is a strategy the Company has effectively deployed in previous exceptional environments.

The largest component of our fixed cost base is labour. The Board of Directors and the Senior Management of the Company have reduced salaries. Where available, economic unemployment schemes have been utilised to match workforce to operating rates whilst protecting incomes. Further steps have been taken where necessary.

After labour, the largest fixed cost is repairs and maintenance (R&M). Clearly during a period of lower asset utilisation the spend on R&M falls - normal per tonne R&M spend continues but the aggregate spending is significantly reduced due to low operating rates.

Finally fixed cost savings have been achieved from countries in which we operate where the currency has depreciated, as well as reduced SG&A expenses such as IT, travel, sales and marketing expenses, consultancy fees etc.

As a result of the actions taken, fixed costs have, on a temporary basis, been reduced in line with lower production rates and as a result fixed costs per tonne in 2Q'20F should be similar to 1Q'20 levels.

8

In addition to the steps taken to reduce operating expenses, the Company has also reduced capital expenditures to minimum levels.

All non-essential capex has been suspended, with the only non-maintenance capital spend being on the close-to-completed Mexico hot strip mill project, agreed projects in Italy and certain projects to reduce CO2 emissions continue. The aggregate maintenance capex spend falls naturally with the lower operating rates.

Consequently, 2020 FY capex is now expected to be $2.4bn, compared to the initial guidance of approximately $3.2bn. This is a level comparable to the spend in the most recent steel downturn in 2016.

9

Given the lower planned capex, as well as the impact of expected lower cash taxes, the Company now expects the cash needs of the business (including capex, interest, cash taxes, pensions and certain other cash costs but excluding working capital movements) to total $3.5bn in 2020 versus $4.5bn previous guidance.

The cash needs of the business were $1.1bn in 1Q'20, implying that the average over the next three quarters should be approximately ~$0.8bn per quarter.

The Company continues to expect working capital to be a source of cash in 2020, targeting a efficiency driven release of $1bn.

10

Moving to the balance sheet.

Due to the Company's focus on working capital efficiency, particularly as the impacts of COVID-19 became apparent, the investment in working capital during 1Q'20 was limited to $0.1bn.

As a result, net debt increased marginally (by $0.2bn) to $9.5bn as of March 31, 2020. The net debt as of March 31, 2020 was $1.7bn lower as compared to $11.2bn in March 31, 2019.

Liquidity remains healthy and is an important strength for the Company as it navigates this exceptional environment. As of March 31, 2020, the Company had liquidity of $9.8bn, consisting of cash and cash equivalents of $4.3bn and $5.5bn of available credit lines (maturing December 2024, this facility may be further extended for an additional year in December 2020). Additionally, the Company has secured a further $3bn credit facility since the quarter end.

As of March 31, 2020, the average debt maturity was 5.2 years.

11

As previously announced in the 2Q'19 results and in line with our ongoing efforts to optimize our asset portfolio, we have identified opportunities to unlock $2bn of value from the portfolio over the next 2 years. The Company has made good progress to date including stake sale in Gerdau ($0.1bn) and sale of a 50% interest in the shipping business (total $0.5bn net debt impact), of which $0.4bn achieved in 4Q'19 and a further $0.1bn in 1Q'20.

Despite the challenges caused by COVID-19, the asset portfolio optimisation program continues to progress. Given suitable and viable buyers have expressed serious interest in certain assets, the Company remains confident in completing the program as expected by mid- 2021.

12

An important development in 2019 was ArcelorMittal's partnership with Nippon steel to acquire Essar Steel India. The calendar year 2020 began well with AM/NS India achieving strong production and shipment performance in January and February. AMNS India's operations were impacted in March by the COVID-19 pandemic and lockdown measures introduced in India. Despite these impacts, AMNS India reported crude steel production of 1.7Mt (7.0Mt annualized run rate) and EBITDA of $140m ($560m annualized) for 1Q'20. Given the cash needs of the business (i.e. maintenance capex, interest and tax) are less than $250m per annum, the JV is in a good position to translate EBITDA to cashflow.

The JV has made good strategic progress during 1Q'20. Beginning first with the new ten-year term loan agreement with Japanese banks. The proceeds of the loan have been used to refinance in full the amounts borrowed by AMNS in connection with the acquisition of ArcelorMittal Nippon Steel India Limited.

Secondly, AMNS India received NCLT Cuttak approval for its resolution plan for OSPIL (Odisha Slurry Pipeline Infrastructure Ltd) that connects the iron ore beneficiation plant in Dabuna to the pellet plant in Paradip, Odisha.

Furthermore, AMNS India announced the acquisition of the Bhander Power Plant, which will remain captive to AMNS India's steel manufacturing operations at Hazira, and was selected as the preferred bidder for the long-life Thakurani iron ore mine.

13

Moving to an update on the Company's activities in Italy. On March 4, 2020, ArcelorMittal announced that AM InvestCo and the Ilva Commissioners had signed an amendment to the original lease and purchase agreement for Ilva. The Agreement outlines the terms for a significant investment by the Italian Government, equal at least to the remaining liabilities payable by AM InvestCo's against the original purchase price for Ilva.

The amendment Agreement is structured around a new industrial plan for Ilva, which involves investment in lower-carbon steelmaking technologies.

In the event that the Investment Agreement is not executed by November 30, 2020, AM InvestCo has a withdrawal right, subject to an agreed payment.

14

Moving to the topic of capital allocation.

Our principle here is to allocate capital in such a way as to provide resilience and a strong platform for consistent capital returns.

This begins with a robust balance sheet. So the Company will continue to target a net debt level of $7bn. This is the level that the Company believes will support positive FCF and investment grade credit metrics through the cycle.

We will invest in our strengths… but following the acquisitions made in recent periods, the focus of investment will now be on organic brownfield opportunities, such as our Mexico HSM project, as well as measures to optimise our cost base.

And ultimately we are working to return more cash to shareholders. We remain committed to returning a proportion of annual free cash flow once we achieve the $7bn net debt objective. Against the backdrop of significant cost savings measures being taken across the business, the Board has determined it both appropriate and prudent to suspend dividend payments at this time. But once the operating environment normalizes, the intention of the Board is to resume dividends and progressively increase this over time.

15

To conclude. COVID-19 is an unprecedent challenge.

The Company's priority has been to take all the necessary actions to safeguard the wellbeing of our people and to provide support to the extent required in the communities in which we operate

Following that, the Company has rapidly adapted production in-line with the demand environment.

Cash preservation is key in a crisis environment. The Company has again shown its flexibility by reducing the cash needs of the business and reducing capex.

The balance sheet and liquidity position remain strong, allowing the Company to navigate this crisis whilst appropriately maintaining our assets so that we are ready and able to respond to the demand recovery

The remainder of this year will be challenging, but the Company remains confident it has the experience and inherent resilience, to navigate these extraordinary times, securing the wellbeing of our people and ensuring that ArcelorMittal emerges from this crisis as it entered it

- as the world's leading steel Company.

16

17

Attachments

  • Original document
  • Permalink