Ref. No.:01/ FA/ISD/Compliance/2022-23 | Dated: 05.08.2022 |
Listing Department | Corporate Relationship Department, |
National Stock Exchange of India Limited | BSE Limited, Rotunda Building, |
'Exchange Plaza', C-1, Block G, | P J Towers, Dalal Street, Fort, |
Bandra Kurla Complex, Bandra (E), | Mumbai - 400 001. |
Scrip Code - 532555 | |
Mumbai - 400 051. | |
Scrip Code - NTPC | |
Sub: Declaration of Commercial Operation of fifth part capacity of 48.8 MW out of 296 MW Fatehgarh Solar PV Project
Consequent upon successful commissioning, fifth part capacity of 48.8 MW out of 296 MW Fatehgarh Solar PV Project at Jaisalmer, Rajasthan, is declared on Commercial Operation w.e.f. 00:00 Hrs. of 05.08.2022. Now, full capacity of 296 MW has been commissioned.
With this, standalone installed and commercial capacity of NTPC has become 54818 MW, while group installed and commercial capacity of NTPC has become 69183 MW.
Yours faithfully,
(Sandeep Aggarwal)
Chief General Manager (Finance)
Registered Office: NTPC Bhawan, SCOPE Complex, 7, Institutional Area. Lodi Road, New Delhi-110003Corporate Identification Number: L40101DL1975GOI007966, Telephone No.-01124387333,Fax: 011-24361018,E-mail: isd@ntpc.co.in
Website: www.ntpc.co.in
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
NTPC Ltd. published this content on 05 August 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 05 August 2022 05:00:00 UTC.