31 January 2017
ISSUED CAPITAL
Ordinary Shares: 525M
DIRECTORS
NON-EXECUTIVE CHAIRMAN:
Robert Kennedy
NON-EXECUTIVE DIRECTORS:
Kevin Lines Michael Bohm
MANAGING DIRECTOR:
Mark Zeptner
www.rameliusresources.com.au info@rameliusresources.com.au
RAMELIUS RESOURCES LIMITED
Registered Office
Suite 4, 148 Greenhill Road Parkside, Adelaide
South Australia 5063
Tel +61 8 8271 1999
Fax +61 8 8271 1988
Operations Office
Level 1, 130 Royal Street East Perth WA 6004
Tel +61 8 9202 1127
For Immediate Release 31 January 2017 December 2016 Quarterly Activities Report HIGHLIGHTS - OPERATIONS, DEVELOPMENT & EXPLORATIONGroup gold production of 31,367 ounces at an AISC of A$1,464/oz (US$1,098/oz*) (Guidance A$1,100/oz or US$825/oz*). It should be noted that the AISC calculation uses gold sold rather than gold produced, with 25,528 ounces sold in the Quarter and 5,839 ounces on hand at Quarter's end.
First Half FY2017 Group gold production of 67,546 ounces at an AISC of A$1,131/oz (US$848/oz*), on track to meet annual Guidance of 135,000 ounces
Mt MagnetBlackmans open pit - open pit set-up work completed, production commenced
Water Tank Hill underground - approvals received, decline rehab commenced
Stellar open pits - upgraded Mineral Resource announced in December 2016
Mt Magnet Exploration - Mineral Resource modelling underway at Morning Star following further positive RC drilling results (see Exploration section), including;
- 15m @ 3.49 g/t Au from 111m in GXRC1520, incl. 5m @ 6.25 g/t Au
- 4m @ 20.21 g/t Au from 113m in GXRC1525, incl. 1m @ 75.5 g/t Au Vivien
Upgraded Mineral Resource to 854,000 tonnes @ 7.2 g/t for 198,000 ounces, an increase of 45,000 ounces (24%) over previous, after including production-to-date
PRODUCTION GUIDANCE - MARCH 2017 QUARTERGroup gold production for the March 2017 Quarter is expected to be 30-34,000 ounces at an AISC of ~A$1,100/oz (US$825/oz*)
Capital development expenditure of approximately A$10.0M:
Water Tank Hill underground development (Mt Magnet) - A$6.0M
Exploration (Mt Magnet & Vivien) - A$4.0M
HIGHLIGHTS - CORPORATE
Quarterly gold sales A$41.0M at an average sale price of A$1,604/oz
Cash & gold on hand increased to A$95.0M (Sep-16 Qtr: A$88.7M), after A$7.4M capital development expenditure comprising Blackmans open pit set-up (A$0.3M), Water Tank Hill decline rehab (A$3.7M) & exploration (A$3.4M)
At 31 December 2016, forward gold sales consisted of 97,009 ounces of gold at an average price of A$1,673/oz over the period to June 2018
Nil corporate debt
* exchange rate assumed 0.75 US$ : A$
ABOUT RAMELIUS
Figure 1: Ramelius' Operations & Development Project LocationsRamelius owns the Mt Magnet gold mining and processing operation and is operating the high grade Vivien underground gold mine near Leinster, in Western Australia.
PRODUCTION SUMMARY
Units | December 2016 Quarter | |||
Mt Magnet | Vivien | Kathleen Valley | Group Total |
t | 325,008 | 51,826 | ‐ | 376,834 |
t | 366,341 | 71,432 | 15,790 | 453,563 |
g/t | 1.10 | 7.03 | 3.85 | 2.13 |
% | 91 | 97 | 97 | 94 |
oz | 11,745 | 15,622 | 1,884 | 29,251 |
Table 1: Gold Production and Financial Information
Ore mined (high grade) |
Ore processed |
Head grade |
Gold recovery |
Gold recovered |
Fine gold poured |
Cash operating costs^ |
Cash operating cost (C1) ^ |
Gold sales |
All‐In Sustaining Costs (AISC) *^ |
AISC^ |
oz | 12,674 | 16,524 | 2,169 | 31,367 |
A$M | 30.2 | |||
A$/oz | 962 |
oz | 25,528 |
A$M | 37.4 |
A$/oz | 1,464 |
A$M | 41.0 |
A$/oz | 1,604 |
Gold sales
Average realised gold price* as per World Gold Council guidelines
^ net of by‐product credits
H1 FY17
Group Total
600,524 |
939,488 |
2.36 |
94 |
67,293 |
67,546 |
55.2 |
817 |
64,768 |
73.3 |
1,131 |
106.1
1,639OPERATIONS
Mt Magnet Gold Mine (WA)
Mining continued in the Galaxy Mine Area throughout the Quarter with the transition from the Perseverance open pit to the Titan open pit almost completed (refer Figure 2). The bulk of total material movements were carried out in Titan (refer Figure 3), with low strip ratio, smaller volumes of material mined from the lowermost benches of Perseverance. The Perseverance open pit is expected to be completed early in the March 2017 Quarter.
Mining activity ramped up at the Blackmans open pit (refer Figure 4), located 30km north of Mt Magnet. Removal of much of the flat-lying laterite ore was carried during the Quarter, with ore haulage commencing in November 2016.
Figure 2: Mt Magnet key mining & exploration areasClaimed high-grade ore mined at Mt Magnet was 325,008 tonnes @ 1.51 g/t for 15,798 ounces with mill reconciled production (including the addition of stockpiled and Titan low grade) of 366,341 tonnes @ 1.10 g/t for 11,745 ounces recovered.
Total mill production (refer Figure 5), including Kathleen Valley and Vivien ore, was 453,563 tonnes @ 2.13 g/t for 29,251 ounces recovered at 94.3% recovery. A scheduled 4-day SAG mill re-line was completed in December 2016, with the next such shutdown not scheduled for approximately six months, depending on the actual wear rate of the mill liners and lifters.
Figure 3: Titan open pit cutback, looking east Figure 4: Blackmans open pit, looking northGold production (refer Figure 6) met Guidance of 31-35,000 ounces, with 31,367 ounces of fine gold poured for the Quarter. Cash costs for the period increased to A$962/oz and AISC also increased to A$1,464/oz (Guidance A$1,100/oz). This was primarily a result of lower overall gold production, which in part was due to over-performance from Kathleen Valley in the September 2016 Quarter leading a reduction in production in the December 2016 Quarter as the project was completed early. In addition to this, AISC is calculated on gold sold as opposed to gold produced (i.e. 25,528 ounces sold versus 31,367 ounces produced). The difference between gold sold and gold produced does tend to even out over the course of the year, with timing of actually pouring and selling gold dependent on when the end of Quarter actually falls. This is evidenced by the fact that First Half FY2017 gold production is 67,546 ounces @ an AISC of A$1,131/oz, closer to the gold sold figure of 64,768 ounces.
Production for the March 2017 Quarter is expected to be between 30,000 and 34,000 ounces. The midpoint of forecast production (32,000oz) is expected to be delivered at an AISC of A$1,100/oz.
Ramelius Resources Limited published this content on 31 January 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 30 January 2017 22:54:08 UTC.
Original documenthttp://www.rameliusresources.com.au/sites/4ea12f9550ee853e00000006/contents/content_instance/588fc30050ee85326600001e/files/20170131_December_2016_Quarterly_Activities_Report.pdf
Public permalinkhttp://www.publicnow.com/view/64775EE2E91F230B09D4402394A4AA6B62939E33