Highlights:
(All dollars USD)
- Large, long-life project with 31.2 million pounds produced over 31 years
- Low initial capital costs of
$47.5M - Unit operating costs (including taxes and royalties) of
$27.70 /lb and ASIC (all in sustaining costs) of$34.83 /lb - Pre-income tax IRR of 62% and NPV (8%) of
$278 million (at$75 /lb U3O8) - Post-income tax IRR 56% and NPV (8%) $239 million (at
$75 /lb U3O8) - Life of Project post-income tax cash flow exceeds
$1 billion - Upside opportunities include:
- Potential for accelerated development of the resource beyond one million pound per annum straight line case outlined in the PEA; existing license allows for a 3-million-pound capacity at planned CPP (Central Processing Plant);
- Potential for enhanced recoveries (PEA assumes recovery of 68% of the resource in the production area) or expansion of the current resource through infill and exploration drilling;
- Inclusion of Crownpoint resource in future production planning; and
- Realized uranium prices more than
$75 /lb pricing assumptions used in the PEA; for example, at a spot price of$90 /lb after-tax NPV (8%) is$294,497,000 .
"Laramide is pleased with the results described in this PEA analysis of the
Summary of Economics
The base case economic assessment results in a pre-income tax internal rate of return ("IRR") of 62% and a pre-income tax net present value ("NPV") of
The economic assessment reflects the development of a steady state 3,000 gpm (gallons per minute) in situ recovery (ISR) operation, which includes Churchrock Satellite Plants, Crownpoint CPP (Central Processing Plant), and associated wellfields near Churchrock,
Following an initial capital cost of
The capital and operating cost estimates for ISR mineral recovery and yellowcake production in the PEA are based on factored costs from other comparable ISR operations, judgment, and analogy. Although there was some previous commercial underground mining production experience at Churchrock area, this Technical Report concerns only the ISR method for the U3O8.
An economic analysis was performed using the assumptions outlined in this News Release. The SLR QPs note that, unlike Mineral Reserves, Mineral Resources do not have demonstrated economic viability. This PEA is preliminary in nature and is based on Inferred Mineral Resources that are considered too geologically speculative to have modifying factors applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that this economic assessment will be realized.
Summary of Capital Costs for 31.2 Mlb LOM Production Schedule (Q1 2022 US dollar basis) | |
Initial Capital Cost (Year -4 through Year 1) | Total ( |
Pre-production Permitting | |
Restoration Demonstration | |
Wellfield Cost (SE1/4 of Section 8 only) | |
Satellite IX Plant | |
Elution Plant | |
Environmental | |
Total Direct Costs | |
EPCM / Owners / Indirect Cost | |
Contingency | |
Sustaining Capital (Year 2 through Year 37) | |
Total Capital | |
Reclamation and Closure | |
Total Capital + Reclamation and Closure |
The LOM average operating cost includes mineral recovery, on-site yellowcake production with hauling cost to Laramide's Crownpoint Processing Facility approximately 22 miles from Churchrock, general and administration, and freight of the product from the CPP to a point of sale, along with various royalties and taxes.
LOM Operating Cost Estimate | ||
Item | LOM Operating Cost | LOM Unit Operating Cost |
Wellfield + Satellite IX Plant Ops | ||
Elution Plant Ops | ||
Waste Management | ||
Restoration Ops | ||
G&A | ||
Capitalized Operating Costs | ||
Total Site Operating Costs | ||
Total Production Costs | ||
Royalties | ||
New Mexico Severance Tax | ||
Total Operating Costs |
Project Description and Resources
The history of exploration and mine development activities for the
As of the effective date of this report, Laramide and its predecessor companies have completed a total of 1,701 holes totaling 1,867,562 ft, from 1957 to 2023, of which 1,694 drill holes were used to prepare the Mineral Resource estimates. The Churchrock project area consists of all or portions of eight sections of land totaling approximately 4,683 acres. The properties are accessible from
Table 1 summarizes the Mineral Resource estimate for the Project (by Section) prepared by SLR, based on drill hole data available as of
Mineral Resources totaling 33.9 million tons at an average grade of 0.075% eU3O8 containing 50.8 million pounds U3O8 (inferred) were reported in 20171. The Churchrock Mineral Resource Estimate was based on results of several historical surface rotary drilling campaigns from 1957 to 1991 and completed utilizing the GT contour method, an industry standard for estimating uranium roll-front type deposits hosted within groundwater-saturated sandstones. The mineralization at the Project has been previously shown to be amenable to ISR techniques. No Mineral Reserves have been estimated for the Project.
Table 1: Summary of Mineral Resources by Section2
Classification | Sand Unit | Tonnage (Tons) | Grade | Contained |
Inferred | Section 4, T16N-R16W | 9,896,000 | 0.071 | 14,090,000 |
Section 7, T16N-R16W | 2,500,000 | 0.058 | 2,910,000 | |
Section 8, T16N-R16W | 6,472,000 | 0.079 | 10,220,000 | |
Section 9, T16N-R16W | 3,393,000 | 0.096 | 6,510,000 | |
Section 17, T16N-R16W | 4,518,000 | 0.074 | 6,710,000 | |
Section 12, T16N-R17W | 4,768,000 | 0.060 | 5,700,000 | |
Section 13, T16N-R17W | 2,331,000 | 0.100 | 4,680,000 | |
Total Inferred | 33,879,000 | 0.075 | 50,820,000 |
____________________________________ |
1 ASX: Laramide announces 51 Million Pounds Mineral Resource Estimate on the |
2 1. CIM (2014) definitions were followed for Mineral Resources. |
2. Mineral Resources are reported at a GT cut-off of 0.5 ft-% eU3O8. |
3. A minimum thickness of 2.0 ft was used. |
4. A minimum cut-off grade of 0.02% eU3O8 (based on historical mineral recovery costs and parameters from the district) was used. |
5. Internal maximum dilution of 5.0 ft was used. |
6. Grade values have not been adjusted for disequilibrium. |
7. Tonnage factor of 15 ft3/ton based on historical used by the mineral recovery operators was applied. |
8. Mineralized areas defined by isolated or widely spaced drill holes, or located within the area previously subject to past production were excluded from the estimate. |
9. Totals may not add due to rounding.
|
Technical Report and Qualified Person
Technical information contained in this news release has been reviewed and approved by
This PEA demonstrates a business case for the further advancement of the Project. Certain licensing/permitting issues remain to be resolved and further technical studies are recommended to validate Mineral Resources and hydrological assumptions.
The Churchrock Project PEA has been prepared in accordance with the requirements of NI 43-101 by
Follow us on Twitter @LaramideRes
Laramide is focused on exploring and developing high-quality uranium assets in
The
In
This release includes certain statements that may be deemed to be "forward-looking statements". All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expect, are forward-looking statements. Forward-looking statements are frequently, but not always, identified by words such as "expects", "anticipates", "believes", "plans", "projects", "intends", "estimates", "envisages", "potential", "possible", "strategy", "goals", "objectives", or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions. Actual results or developments may differ materially from those in forward-looking statements. Laramide disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, save and except as may be required by applicable securities laws.
Since forward-looking information address future events and conditions, by their very nature they involve inherent risks and uncertainties. Actual results could differ materially from those currently anticipated due to a number of factors and risks. These include, but are not limited to, exploration and production for uranium; delays or changes in plans with respect to exploration or development projects or capital expenditures; the uncertainty of resource estimates; health, safety and environmental risks; worldwide demand for uranium; uranium price and other commodity price and exchange rate fluctuations; environmental risks; competition; incorrect assessment of the value of acquisitions; ability to access sufficient capital from internal and external sources; and changes in legislation, including but not limited to tax laws, royalties and environmental regulations.
SOURCE
© Canada Newswire, source